The report provided an
update on the housing development programme.
Decision
of Executive Councillor for Housing and Homelessness
i.
Noted the continued progress on the delivery of the approved
housing programme.
Reason for the Decision
As set out in the Officer’s report.
Any Alternative Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee received a report from the Interim Assistant Director
Development.
The Committee made the following comments in response to the report:
i.
Welcomed the work done regarding the provision of
homes for Ukrainian refugees.
ii.
Requested that future reports provided information
on wheelchair accessible homes by bedroom size.
The Interim Assistant Director Development said the following in
response to Members’ questions:
i.The tables
within the report showed the different stages the various housing developments
were at. Agreed to work with councillors to see if different descriptions of
the stages of development could be used, so that this information was more user
friendly.
ii.Archaeological
investigations (referred to on p123 paragraph 6.3 of the agenda) were sometimes
required as part of a planning application approval. Officers worked with the
County Council’s Archaeological Department and consultants to comply with any
planning conditions regarding a site’s archaeology.
The Committee unanimously resolved to endorse the recommendation.
The Executive Councillor
approved the recommendation.
Conflicts of Interest Declared by the Executive Councillor (and any
Dispensations Granted)
No conflicts of interest were
declared by the Executive Councillor.