Decision Maker: Executive Councillor for Planning, Building Control, and Infrastructure
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Environment Scrutiny descision whether to proceed with the stated project, further to receiving the consultation results.
Matter for Decision
The project aims to provide one thousand additional secure cycle parking
spaces in the heart of the city centre. This is planned to be achieved through
the provision of:
i.
Localised on-street cycle parking throughout the
city centre where space allows and the demand for cycle parking is high.
ii.
A third undercover secure cycle park, similar to
those at Park St and Grand Arcade car parks. This report provides an appraisal
of the on-street element of the project. Feasibility work is currently underway
to look at the options for a third undercover secure cycle park.
Decision
of Executive Councillor for Planning and Climate Change
Financial
Recommendation
i.
Approved the commencement of the on-street cycle
parking proposals, which is already included in the Council’s Capital &
Revenue Project Plan. The total estimated cost of the on-street proposal is
£235,000 funded from the City Centre Cycle Parking Project capital allocation
SC549.
Procurement
Recommendations
Approved the carrying
out and completion of the procurement of:
ii.
The construction of the proposed
cycle parking locations as listed in table 1.0 and detailed in the package of
drawings in Appendix C of the Officer’s report; subject to the following sites
being deferred pending further information (ie equality impact assessments and
commuted sum) being presented to a future Environment Committee for further
consideration:
· Pease
Hill 014-018/000/102.
· Guildhall
Street 014-018/000/103.
· Kings
Parade 014-018/000/004.
· Jesus
Lane 014-018/000/008.
· Wheeler
Street.
iii.
Consultation approved and the
results to be presented to a future Environment Committee for the additional
new sites included in table 1.0 namely:
·
St Mary’s Street.
·
East Road.
· Peas Hill/Wheeler
Street.
Subject to:
· The permission of
the Director of Resources being sought prior to proceeding if the quotation or
tender sum exceeds the estimated contract.
· The permission
from the Executive Councillor being sought before proceeding if the value
exceeds the estimated contract by more than 15%.
Reason for the Decision
As set out in the Officer’s report.
Any Alternative Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee received a report from the Project Delivery &
Environment Manager.
The Committee made the following comments in response to the report:
i.
Expressed concern
regarding the loss of city centre disabled parking spaces and the impact this
would have on members of the public wishing to use them.
ii.
Suggested the city
centre had some existing access issues for people with mobility and visual
impairments. For example, street clutter and cycling in pedestrian areas.
Increasing cycle parking provision could exacerbate these issues.
iii.
Expressed concern at the
proposed increase of cycle parking provision in heritage areas.
In response to Members’ questions the Director of Environment and
Project Delivery & Environment Manager said the following:
i.
The needs of pedestrians, cyclists and motorists
needed to be balanced.
ii.
Various organisations had been included in the
parking provision consultation, including Camsight.
iii.
An old version of the equality impact assessment
was included in the agenda pack. Details have since been updated. The new
report could be circulated upon request.
iv.
The impact of advert boards on thoroughfares could
be reviewed.
v.
Disabled parking bays could be kept on Peas Hill if
cycle parking provision was reduced.
vi.
Eden Street was erroneously referred to as Elm
Street on P108 of the agenda pack.
Councillors requested a change to recommendation
(ii). Councillors O’Reilly and Saunders formally proposed to amend the
following recommendation from the Officer’s report (amendments shown as bold):
ii.
(Procurement) The construction of the
proposed cycle parking locations as listed in table 1.0 and detailed in the
package of drawings in Appendix C of the Officer’s report; subject to the following sites being deferred pending further
information (ie equality impact assessments and commuted sum) being presented
to a future Environment Committee for further consideration:
· Pease Hill 014-018/000/102.
· Guildhall Street 014-018/000/103.
· Kings Parade 014-018/000/004.
· Jesus Lane 014-018/000/008.
· Wheeler Street.
The Committee unanimously approved this amended
recommendation.
The
Committee resolved unanimously to endorse the recommendations as amended.
Conflicts of Interest Declared by the Executive Councillor (and any
Dispensations Granted)
No conflicts of interest
were declared by the Executive Councillor.
Publication date: 29/10/2013
Date of decision: 08/10/2013