***ROD-Approval of funding for the construction of Cherry Hinton Hub

Approval of £841,518 funding for Cherry Hinton Hub.

Decision type: Key

Reason Key: Expenditure > £300,000;

Decision status: Recommendations Approved

Notice of proposed decision first published: 04/04/2023

Decision due: Before 3 Jul 2023 by Executive Councillor for Transformation

Contact: Allison Conder, Strategic Project Manager Email: Allison.Conder@cambridge.gov.uk.

Background Information: A provisional sum for the Cherry Hinton Hub scheme was included in the Feb 2023 Budget Setting Report. Officers were aware that there would be insufficient time to complete RIBA stage 3 and 4 design work and to prepare a detailed Bill of Quantities and so the provisional sum was based on a scheme estimate from the appointed contractor.