Council and democracy
Home > Council and Democracy > Issue
Record of Executive
Decision
Approval of funding
for the construction of Cherry Hinton Hub.
Decision of: Councillor Davey, Executive
Councillor for Finance Resources and Transformation
Reference: 23/URGENCY/S&R/07
Date of decision: 03/04/2024 Date Published on website: 04/04/23
Decision Type: Key
Matter for Decision: Approval of funding
for the construction of Cherry Hinton Hub (planning ref: 19/1713/FUL)
Why the Decision had to be made (and any
alternative options): A provisional sum for the Cherry Hinton Hub scheme was
included in the Feb 2023 Budget Setting Report. Officers were aware that there
would be insufficient time to complete RIBA stage 3 and 4 design work and to
prepare a detailed Bill of Quantities and so the provisional sum was based on a
scheme estimate from the appointed contractor.
A detailed Bill of Quantities from the
contractor was then received 17th March 2023, but this was too late
to achieve the 10th March 2023 final report
deadline for the next Strategy and Resources Committee on 27th March
2023.
Two risks for the council now mean that an
out of cycle decision is required before any future scrutiny committees or as
part of the council’s next standard budget setting process:
1.
Construction regulation changes are due to come into force on 15th
June 2023 and will mean additional cost from; changes to the building fabric
specification; redesign work to accommodate the fabric changes; cost
reappraisal work.
2.
The time delay from completing the new regulation works will mean that
planning approval will lapse before contracting can be completed and the
contractor mobilised to start on site. This in turn will mean additional costs
are incurred from the impact of inflation (9.4% currently) while a new planning
approval is obtained (this originally took 12 months)
The
estimated cost impact if these two risks are not mitigated through the
implementation of an urgent decision out of cycle decision, is an estimate £150 - £200k additional capital funding requirement
which would create a £991,518 funding gap to be able to implement the scheme, rather than a
gap of £841,518 if we implement before 15th June 2023.
The Executive Councillor’s decision:
Approval of £841,518 funding for Cherry Hinton Hub.
Reason for the decision: As detailed in the
Officers supporting briefing report Document Out of Cycle Decision - Approval of funding for the
construction of Cherry Hinton Hub - Cambridge Council
Scrutiny Consideration: The Chair and
Spokespersons of Strategy and Resources Scrutiny Committee were consulted prior
to the action being authorised.
Conflict of interest: None
Comments: Part 4C section 6.1 of the
Councils Constitution, permits decisions to be taken which are outside of the
budget framework if the decision is:
The next available Strategy and Resources
Committee is 3rd July 2023 which is too late. The next available
ordinary Full Council meeting is 25th May which is too late to
completing contracting and achieve a start on site by 15th June 2023
ahead of construction regulation changes and planning approval lapsing.
The decision will be reported back to
S&R Committee on 3rd July 2023, and Full Council on 25th
May 2023.
Spokes Councillors also raised questions:
Cllr Naomi Bennett raised concerns about
transport links to the proposed hub and was particularly interested in buses
and a safe walking path accessible by power chairs, mobility scooters and
prams. Also acknowledged concerns which had been raised by cyclists.
Response
The County Council as a statutory planning
consultee were responsible for providing the bus services and were also
responsible for highways safety issues. Confirmed that the County Council
submitted no comments or requirements for offsite highways improvements in
relation to the Hub scheme.
The new hub would be located right in the
centre of Cherry Hinton and was intended to provide direct access to new
community facilities for Cherry Hinton residents who lived within a 15 minute walk-time catchment. There was currently no
vehicular parking on site for the library, and this would remain unchanged,
with the expectation that most people who used the hub and the community café
would arrive on foot or by bike, to reduce congestion and improve air quality, health and road safety. At the front of the building
there would remain a blue-badge parking space and the hub scheme included new
cycle parking proposals in line with LPA requirements (13 visitors and 3 staff
spaces, with dedicated extra-wide stand for cargo bike). Pedestrian access to
the library would be maintained from the High Street, with the new main
entrance angled towards the primary junction to Colville Road. In order to maintain the internal level with the existing
library premises, an external ramp / sloping footpath was proposed along the
west elevation.
Question(s) from Cllr Tim Bick:
(1) Wanted to understand the difference to
the built form if the development was carried out after changes in building
regulations were introduced.
(2) Asked who would take on the management
and running costs of the completed facility.
Response
In summary, additional time and cost would
be incurred for the redesign.
A rough estimate included:
Revisions required
Mechanically:
•
Additional PV panels
•
Relooking at Part L and BRUKL calculations/modelling
•
Time spent on redesigning some mechanical & electrical aspects
Electrically:
•
New lighting design
•
Split metered distribution board
Architecturally:
•
Time spent on redesigning some architectural build-up as a
result of the calculations/modelling done by mechanical, electrical and
plumbing team.
The Community Hub will be managed by the
Cherry Hinton Community Benefit Society. The County Library service will
operate from the building.