Council and democracy
Home > Council and Democracy > Issue
Matter for Decision
This report
presents, for all Portfolios:
i.
A
summary of actual income and expenditure compared to the final budget for
2022/23 (outturn position)
ii.
Revenue
and capital budget variances with explanations
iii.
Specific
requests to carry forward funding available from budget underspends into
2023/24.
The outturn report
presented reflects the Executive Portfolios for which budgets were
originally approved (which may have changed since, for example for any changes
in Portfolio responsibilities).
Decision of the Executive
Councillor for Finance & Resources:
i. To carry forward requests totalling
£1,391,800 of revenue funding from 2022/23 to 2023/24, as detailed in Appendix
C. These are carry forward requests in excess of £50k. Requests up to and
including £50k which total £176,070 are approved via delegated authority to the
Chief Financial Officer.
ii. To approve additional budget in
2023/24 of £80k to the Climate Change Fund funded from reserves, as detailed in
Paragraphs 3.6 to 3.8 below.
iii. To approve the allocation of £200k from
the General Fund reserve to establish Greater Cambridge Impact (GCI) as
detailed in Paragraphs 3.9 and 3.10 below.
iv. To approve the allocation of £218k in
2023/24 from the General Fund reserve to fund the additional resource required
to enable the delivery of key programmes and projects within the Place Group.
The allocation required will increase to £267k in 2024/25 and £281k 2025/26
onwards as detailed in Paragraphs 3.11 below.
v. To carry forward requests of
£81,444,000 of capital resources from 2022/23 to 2023/24 to fund rephased net
capital spending, as detailed in Appendix D.
Reason for the Decision
As set out in the Officer’s report.
Any Alternative Options Considered and Rejected
Not applicable.
Scrutiny Considerations
The Chief Finance Officer said the following in response to
Members’ questions:
i.
General
policy was to move business rates growth into reserves. This was because there
was always risk in relation to the amount of business rates growth that would
be received. This had achieved a high level of reserves and had enabled the
Council to look at reserves as a source of capital funding for the Place Group
schemes, for example reserves could be used as capital schemes are brought
forward for the modernisation and decarbonisation of the Guildhall, Market
Square, and other significant projects. This meant that these projects could be
carried out without having to borrow to do so.
ii.
While
the Council held high levels of reserves at the moment, they would also be used
going forward while going through the Transformation programme. The Council
currently has a policy of maintaining £7 million in the General Fund reserve as
a prudent minimum balance.
iii.
The
Settlement Funding Assessment was funding from Government which came mainly
from Business Rates. That figure was dependant on the allocation of funding
from the Government. The expectation is that level will continue until the fair
funding review is implemented. We are expecting this to be 2026-2027.
iv.
Appropriations
from earmarked reserves included a variety of items, including grant funding.
The final budget was in line with the outturn position, that is as planned.
Therefore, the amounts would vary year on year depending on level of grants the
Council received and the use of earmarked reserves.
v.
It
had been difficult to get take up of Sustainable Warmth Grants. There had also
been a lack of available contractors. There was a possibility that the grant
money would need to be repaid to the Government for what was remaining in due
course. There were Officers working in this area in hopes of minimising that.
vi.
A
detailed report would need to be written reporting on how agile the Council had
been regarding the Sustainable Warmth Grant. That report would need to be
written by a different department, and likely go to a different committee, most
likely Housing Scrutiny Committee.
vii.
Regarding
variances in the budget, this was reviewed monthly. There was a quarterly
report produced covering both revenue and capital. This report was presented to
the Executive, the Leadership Team, and the Senior Management Team.
viii.
Regarding
budgets, when the budget was set at the beginning of the year Officers avoided
tweaking it too often because it then became difficult to understand the forces
that were impacting the budget. Budgets were adjusted at budget setting time
based on proposals put forward.
The Leader of the
Council said the following in response to Members’ questions:
i.
When
quarterly budgets were reported they were reviewed by the Executive who would
raise any issues they may have at that time.
ii.
If
there was to be interrogation over each individual item in the budget, when
reviewing the budget setting process this was something that could be
considered. The Leader stated he would speak to the Chief Executive about this
after the meeting.
The Chief Executive
said the following in response to Members’ questions:
i.
Regarding
Sustainable Warmth Grants, the Council had been in contact with BEIS about how
the scheme was set up and eligibility, this had proved to be a barrier. Ministers had responded and extended these
schemes. This scheme is managed by Cambridge City Council for all of
Cambridgeshire. BEIS had extended the timeline in which the money could be
used. This was now being focused on by Officers. There was a better supply
chain in place, and it was being advertised better. It was important that the
money was spent.
The Director of City
Services said the following in response to Members’ questions:
i.
Bereavement
services had reduced income due to increased competition in the market and the
local area. However, the service was still making a profit. There was currently
work being done to see what the future of the service would be.
ii.
Regarding
the new City Services directorate, would be looking into garage and crematorium
services.
Committee Manager Note: Regarding Warm Home Grants
The rephasing of the grant fund is not for the full
amount, but only applies to a much lower amount of the funding that has already
been committed to jobs.
For clarity, all funding was due to be spent by March
2023. However DESNZ granted a “managed closure” extension which allowed us to
carry over funding for jobs already in the pipeline, and where these jobs could
be completed on site by end of April 2023 for off gas properties and end of
September 2023 for on gas. The total spend and number of properties in this
managed closure has already been signed off by DESNZ. We can not use this
rephasing of the budget to bring in new jobs, only complete those in the
pipleline. Therefore our focus for this funding is to work with the contractors
to get these final properties completed by the deadlines agreed.
Any new leads and engagement activity is being fed into
alternative and new funding streams (i.e. ECO and HUG Phase 2)
We have already retuned the majority of the identified
underspend, and should currently just hold the equivalent of the estimated value
of work to cover the manage closure (+20%). However I am not sure if this is
return already made is reflected in the reports. Karen and Joanna Taylor were
looking into it.
On this basis there is no scope to spend more of this
particular funding, apart from ensuring all jobs in the pipeline are completed
on time which we are managing on a daily basis.
Provided by Justin Smith, Environmental Projects Team
Leader after the conclusion of the meeting.
The Committee unanimously endorsed the recommendations.
The Executive Councillor approved the recommendations.
Conflicts of Interest Declared by the Executive
Councillor (and any Dispensations Granted)
No conflicts of interest were declared by the Executive
Councillor.