The report presented details of anticipated variances from budgets,
where resources were requested to be carried forward into the 2023/24 financial
year in order to undertake or complete activities
anticipated to have taken place in 2022/23.
Decision
of Executive Councillor for Housing
i.
Agreed the provisional carry forward requests, totalling
£440,840 as detailed in Appendix A, subject to the final outturn position.
Reason for the Decision
As set out in the
Officer’s report.
Any Alternative
Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee
received a report from the Assistant Head of
Finance and Business Manager.
The Head of Housing Maintenance and Assets said the following in
response to a Member’s question:
i.
The delay with the Water Conservation Project was
due to a member of staff leaving and a procurement exercise being carried out.
The request to carry forward funding was to allow the project to conclude. The
Net Zero Retrofit Project Officer was now undertaking the work with
consultants. An interim report was expected at Easter with a final report two
weeks later. It was hoped that water conservation trialling measures would be
started in May.
The Committee resolved by 10 votes to 0
to endorse the recommendation.
The Executive Councillor
approved the recommendation.