The
Committee received a report from the Senior Engineer regarding the
Environmental Improvement Programme (EIP). The report requested that the
Committee determined which of the proposed new second round EIP applications
should be allocated funding as part of the 2016-17 Environmental Improvement
Programme, from those listed in Appendix A of the Officer’s report.
In response to Members’ questions the Senior Engineer answered:
i.
£10,000 - £20,000 of funding was available for projects to bid for.
ii.
Section 5 of the Officer’s report set out projects that were not yet
ready to come forward.
Councillor Cantrill suggested Area Committee Councillors liaise after
the meeting on how best to encourage projects to come forward and apply for
funding rather than lose it. Although it was not desirable to use EIP funding
to replace trees, this was the only way currently as other funding had run out.
Following discussion, Members resolved
(unanimously) to:
2.1
Allocate £2,000 of remaining EIP budget
for 2016-17 to the list of proposed projects in Appendix A of the Officer’s
report.
2.2
Approve those
projects for implementation, subject to the schemes being deliverable,
obtaining consents necessary, positive consultation where required and final
approval by Ward Councillors.