Council and democracy
Home > Council and Democracy > Issue
Decision
of: |
Executive Councillor for Public Places: Councillor Andrea Reiner |
||
Reference: |
13/URGENCY/ENV/8 |
||
Date
of decision: |
31/12/13 |
Recorded
on: |
31/12/13 |
Decision
Type: |
Non
Key |
||
Matter for
Decision: |
1.0 Financial
recommendations – 1.1 The
Executive Councillor is asked to approve the commencement of the Parker’s
Piece Lighting Scheme as detailed in the Officer’s report, the funding for
which is already included in the Council’s Capital & Revenue Project
Plan. 1.2 The total
estimated cost of the project is £60,000 funded from the capital plan
allocation SC584. 1.3 The on-going
revenue costs for the project will be incorporated within existing revenue
budgets. 2.0 Procurement
recommendations: The Executive
Councillor is asked to approve the carrying out and completion of the
procurement of: 2.1 The
installation of the lighting on Parker’s Piece in accordance with the details
in the Officer’s report. 2.2 Subject to: - The permission
of the Director of Resources being sought prior to
proceeding if the quotation or tender sum exceeds the estimated contract. - The permission
from the Executive Councillor being sought before proceeding if the value
exceeds the estimated contract by more than 15%. |
||
Why the decision had to be made
(and any alternative options):
|
The project
proposes the installation of additional lighting columns along the two
diagonal path sections that are adopted public highway across Parker’s Piece. |
||
The Executive Councillor’s decision(s): |
1.0 Financial
recommendations – 1.1 The
Executive Councillor approved the commencement of the Parker’s Piece Lighting
Scheme as detailed in the Officer’s report, the funding for which is already included
in the Council’s Capital & Revenue Project Plan. 1.2 The total
estimated cost of the project is £60,000 funded from the capital plan
allocation SC584. 1.3 The on-going
revenue costs for the project will be incorporated within existing revenue budgets. 2.0 Procurement
recommendations: The Executive
Councillor approved the carrying out and completion of the procurement of: 2.1 The
installation of the lighting on Parker’s Piece in accordance with the details
in the Officer’s report. 2.2 Subject to: - The permission
of the Director of Resources being sought prior to proceeding if the
quotation or tender sum exceeds the estimated contract. - The permission
from the Executive Councillor being sought before proceeding if the value
exceeds the estimated contract by more than 15%. |
||
Reasons for the decision: |
As set out in the Officers Report. |
||
Scrutiny consideration: |
The Executive Councillor and Spokesperson were consulted prior to the decision being made.
|
||
Report: |
See attached memo.
|
||
Conflicts of interest: |
No conflicts of interest were declared by the
Executive Councillor.
|
||
Comments: |
None. |