Council and democracy
Home > Council and Democracy > Agenda item
Application No: 26/02109/FUL
Site Address: Christs College Library Christs College St
Andrews Street
Cambridge
Description: Demolition of 1970s library and
replacement with new library, social and study spaces including re-provision of
bridge to the Bodley Library. Alterations to kitchen, Upper Hall and adjacent
areas including new plant, access improvements and alterations to wc, provision in the south east
range of Second Court. Re-landscaping of Bath Court and ancillary works,
installation of temporary kitchen and dining facility in Second Court for the
duration of the works.
Applicant: Lord
Simon McDonald
Agent: Ms Ellie Drozdowska
Address: Turley, 8 Quy Court Colliers Lane
Cambridge CB23 9DH
Case Officer: Dominic
Bush
Lead Petitioner: Christ's
Lane Action Group
The grounds for asking for a Forum on this application
are as follows:
The Christ’s Lane Action Group supports the provision of a
new library for Christ’s College. We do not object in principle to a new
library. We object to this particular scheme.
Application 26/02109/FUL is the same physical building as the previous
application (25/02161/FUL). Rather than defend the judicial review of that
permission, the Council and the College signed a Consent Order on 28 April 2026
agreeing that it should be quashed on all four grounds and that the Action
Group’s costs should be paid; the Court has not yet made a final quashing
order, and the substantive hearing remains listed for 20 October 2026. The
resubmission reproduces the same reasoning, and now goes further, recharacterising as a “minor beneficial impact” the very
bulk and massing that the heritage consultees had identified as harmful. A
Development Control Forum is needed so that residents, retailers, the College
and the Council can discuss how a new library can be delivered without that
harm.
1) Historic
England, the Victorian Society and the independent heritage consultant Alec
Forshaw each assessed this scheme and found harm, and none of them has
withdrawn that advice. Historic England (29 July 2025) found the building “too
big, overdominant” and confirmed on 1 September 2025
that “the overall massing of the building remains unchanged”; the Victorian
Society (August 2025) suggested reducing the height by approximately half at
each floor to improve the overall scale of the current proposals; and Alec
Forshaw (October 2025) found less-than-substantial harm “at the upper end of
the scale” to the setting of the Grade I listed Bodley Library. These and other
heritage consultees, including the stautory
consultee, the Gardens Trust, have not had the opportunity to respond to the
resubmission’s new claim of a “minor beneficial impact”.
2) The scheme
creates a canyon effect on Christ’s Lane. It places a sheer wall of
approximately 14 metres on the north side of a lane only approximately 6 metres
wide, an enclosure ratio of roughly 2.3:1, far exceeding historic streets such
as Trinity Street and Rose Crescent (approximately 1.5:1). The height further
exceeds the 11.4-metre height limit set for this lane in the 2002 Joint
Planning Brief by around 3 metres. Christ’s Lane is a designated principal
pedestrian route (Local Plan Policy 10) carrying over 10,000 people a day, and
the scheme would turn it into a dark, oppressive corridor.
3) The loss of
daylight is severe and has not been properly assessed. The applicant’s own
evidence shows Vertical Sky Component losses exceeding 50% at 25 windows along
Christ’s Lane and over 90% at four, with the café windows directly opposite
reduced by between 55% and 96%. No BRE 209 (2022)-compliant daylight, sunlight
and shadow-plotting assessment has been provided for the lane as a public
space, and no Construction Management Plan has been submitted for a route with
this footfall.
4) The scheme
offers minimal genuine public benefit or active frontage. Against the harm
identified by the heritage consultees, it offers only a single bench and a
“book-stop”. Benefits offered by previous Christ’s College library schemes
never materialised, including the previously promised green wall. The building
presents a blank, inactive wall to Christ’s Lane where the lane requires active
frontage.
5) The building
qualifies as a Tall Building: it breaks the existing skyline and is
significantly taller than the Bodley Library and First Court, yet no Townscape
and Visual Impact Appraisal has been provided against the specific criteria of
Policy 60 of the Cambridge Local Plan. The scheme also conflicts with Local
Plan Policies 10, 56, 58 and 61 and with NPPF paragraphs 212–215, none of which
can be satisfied while the harm found by the heritage consultees is simply
denied.
6) Credible less
harmful alternatives were before the Council and remain unaddressed. The 2016 basemented Rick Mather scheme was not found harmful by
Historic England, and the Victorian Society expressly contrasted it with the
current scheme; the 2016 design would not be harmful, whereas the current one
has the potential to be. The Victorian Society also recommended aligning floor
heights with the Bodley Library’s oriel window, roughly halving each floor
height. Create Streets further illustrated a basemented
lower-impact route (October 2025). The failure to engage with these options,
one of the grounds conceded in the judicial review, returns unchanged.
Do you think there are changes that could be made to
overcome your concerns?
Yes. The Christ’s Lane Action Group is not objecting in
principle to a new library. The following changes would overcome our concerns:
1) Reduce the
height, mass and scale of the building so that it no longer harms the setting
of the Grade I listed buildings or the character of Christ’s Lane, for example
by aligning floor heights with the Bodley Library’s oriel window as the
Victorian Society recommended, and by revisiting a basemented,
lower-rise approach along the lines of the 2016 scheme.
2) Introduce
genuine active frontage and public benefit onto Christ’s Lane, satisfying Local
Plan policy on this principal pedestrian route, rather than presenting a blank
wall.
3) Provide the
missing evidence and consult on it properly: a BRE 209 (2022)-compliant
daylight, sunlight and shadow-plotting assessment for Christ’s Lane as a public
space, and a Construction Management Plan for the construction period.
4) Bring the
ventilation stacks down to a height subservient to the college’s historic buildings, and demonstrate a comparison between alternative
ways of realising passive ventilation.
5) Undertake and
publish a genuine assessment of less harmful alternatives, including the 2016
Rick Mather scheme, together with a proper Townscape and Visual Impact
Appraisal against Policy 60.
Minutes:
Case by Applicant
1)
The Applicant introduced their presentation by
explaining why they were here, why they wanted to replace the library and why
they did not want to dig a basement.
2)
The application was to demolish the 1970’s
library and replace with a new library, social and study spaces including
re-provision of bridge to the Bodley Library.
3)
There had been a lengthy consultation period
including a previous Development Control Forum held last summer with Planning Permission
granted in November 2025 with written confirmation received the same month.
4)
In December 2025, the Christs Lane Action Group
(CLAG) applied for a Judicial Review (JR) for which the High Court granted
permission to proceed to a full hearing, in March 2026.
5)
The Court had identified the date of 20 October
2026 for the hearing which the college felt was to long a time. It was added that the college looked at the
substance of the Judicial Review which did not touch on the merits of the project
but looked at the procedures and found four shortcomings.
6)
The College had looked at those shortcomings and
thought that they could all be addressed in a second application so that should
a second Planning Application be granted the Council could be confident that it
met the standards of the JR.
7)
Time was of the essence for the College as
students had already bee using a temporary library
for one year.
8)
In regard to the
existing library, Christs College was the only college in Cambridge where all
six of the central elements were around the first court which included the
Porters, Chapel, Masters Lodge, hall, buttery and the library.
9)
In the 1970’ the college built the structure
which was shoddily built with no thought given to the impact on the city as it
faced into the loading bay of Argos at the time and therefore not publicly
facing. It was an ugly building with no public realm benefit.
10)
Over the last fifty years the building had been gradually
deteriorating which had now accelerated.
The original spec gave the building a life span of 50 years which had
now expired and needed to be replaced.
11)
Alternatives had been looked at on the current
college site which had been rejected for both the historic reason of keeping
things together on First Court and secondly, as the library connects Bodley
which was a building from the 1890’s and was the old library and had not been
in use since the current student library was built.
12)
The college wanted to bring Bodley back into use
and have a vital connection with the undergraduate library so that both could
be used simultaneously.
13)
The College needed to replace the library and
the need had been known for some time. A
new library had been proposed 15 years ago when Rick Mather designed a
replacement which received planning permission.
However, funding was not available at the time.
14)
Since then, the building environment had changed
with sustainability and accessibility concerns being a different place with
things that people did not care about 15 years ago they do now.
15)
The key feature of the Mather design was a
basement. On reconsidering the colleges needs, it was concluded that on advice this would
be the least ‘Green’ thing that could be done for three main reasons:
·
Firstly the amount of
embedded carbon. Typically, in a modern
building 40% of embedded carbon was in the basement which the college wanted to
avoid. The only way to ensure a basement
was watertight was to use concrete which is one of the most carbon intensive
building materials.
·
Secondly the site was very close to Grade 1
listed buildings. The Bodley dated from
the 19th Century, but behind the student library was the 16th
Century First Court which had no foundations.
If a basement was dug within inches of this you
would not know what you would find and were likely to have an unpleasant
surprise. Heritage Harm was a the top of the colleges mind and they did not want to
disturb the environment.
·
The third reason was the extra disruption. Many of the objections on the Planning Portal
were about disruption, which was inevitable with a city centre site, with
digging a basement would massively increase that as all of
the material would need to be removed by lorry.
In order to minimise any disruption
it was decided not to include a basement which made the previous design no
longer fit for purpose.
16)
The college had organised an architectural competition
with six entries. The winners Grafton
Architects of Dublin, one of the world’s leading architectural firms who had
come up with a beautiful, sustainable accessible design.
17)
A Student in her final year in the Architectural
Department in support of the application commented that she lived in Cambridge
and was also bringing up her to children in the city. She informed the meeting that:
·
Students needed different areas to work in. Some needed quiet space to concentrate, whilst
others needed somewhere to discuss ideas and work in groups.
·
The current library did not accommodate those
needs which was why many students ended up working elsewhere such as cafes in
hotels so that they could eat and spread out their work. The college could not support this way of
working.
·
As a Member of the Architectural Society at
Christ’s College, she was invited to attend interviews and the selection
process for the new library Competition.
·
The Grafton design responded to the colleges needs
to provide different kinds of study spaces including a lounge, spaces for group
work, social study areas, individual workstations and places where students
could spend an entire day.
·
The design should engage with its
surroundings. The current design was not
isolated and took inspiration from the walls, windows and chimneys of the
buildings around it and also the historic courts and
gardens at the college.
·
The façade at Christ’s Lane responded to the
architectural character of Cambridge through the chimneys and its use of brick
and stone.
·
Inside, the design took you on a journey through
a set of rooms, the Bath Court, green and open to the sky, the social hall
which created a protected hub for students and finally the library itself.
·
As a resident she walked Christs Lane almost
every week with her children. Today the
college side is blank brick wall with no reason for anyone to stop. The project would put windows, people and light
behind the wall for the first time. It
would give views into the library, a bench and an un-arched gate by day and at
night light from the library windows falling gently into the lane.
·
She supported the project as it would give
future generations the kind of library her generation had needed but never
had. A place to study, socialise and
belong.
18)
In regard to heritage
harm and the advice of Historic England, although this was a repeat of the
previous application approved in November 2025.
The Listed Building Consent application was approved at the same time
has not been challenged and still remained valid.
19)
Much has been made about the implied harm to the
setting of the Bodley Library. This 19th
Century addition to the original library is not listed in isolation but was
part of the Grade One listing covering the shole of the entrance court which
dated to the 16th Century and also part of
Second Court.
20)
The college had been very clear and consistent in
its assessment of the heritage impact of the proposals, which was set out in
the heritage statement and carefully considered the impact of the proposals on
all parts of the listed buildings themselves, not just the Bodley, and impact
on their settings and the colleges historic park and gardens and conservation
area.
21)
The design did not just focus on one part of the
building as others had done and sought to draw conclusions on a partial
assessment.
22)
The impact on the Bodley Library, other than the
replacement bridge link, there was no physical attachment or alteration. In that respect, the currents scheme differed
significantly from the 2011 and 2016 Mather scheme which had attached a glazed
roof to glaze over Bath Court which had been forgotten by the Victorian
Society.
23)
The focus of concern about setting appeared to
be in the view on Christs Lance from where the new library would appear taller
that the Bodley. Historic England setting
guidance and stated that the importance of setting lied in what it contributed
to the significance to the setting of the heritage asset or to the ability to
appreciate that significance.
24)
The present library on the Christs Lane side was
bland and utilitarian which was appropriate when it was built to face a private
access lane but was now out of place since the lane was reopened to the public.
25)
The new library would be of high design quality
and designed by one of Europe’s leading architects. It had been endorsed by the design review
panel. It would be further away from the
Bodley, and views would be gained through the new gate into Bath Court allowing
the lower level to be seen.
26)
Evening focusing solely on that view and
ignoring the clear enhancement to Bath Court, and the improvement that would
make to the setting of the Bodley and other parts of the colleges grade one
listing, it was argued that the replacement library would not detract from the significance
of the Bodley or anyone’s ability to appreciate that significance and would be
beneficial.
27)
Even if it was considered that there was some
less than substantial harm caused to the heritage significance of the Bodley by
replacing the library in its setting, this would still need to be weighed with
the other heritage benefits and to the setting and to the significance of the
other parts of listed buildings and conservation area in particular. This was why the college considered the heritage
impact of the proposed library to be beneficial.
28)
The statutory duty with regard to the listed
building was within Section 661 in the Planning Listed Buildings and
Conservation Areas Act, which required that those making decisions about
planning applications to have special regard to the desirability of preserving
a building or its setting or any features of special architectural historic it
possesses.
29)
This special regard had to be assessed as the college
had done and given great weight when considering proposals in the planning
balance. When proposals did lead to less
than substantial harm this needed to be weighed against the public benefits of
the scheme by virtue of paragraph 215 of the Planning Policy Framework. There was no harm to be outweighed anyway
quite the opposite but there were clear benefits.
30)
Those suggesting that there was harm to the
significance of the Bodley caused by the new library and its setting needed to also
consider these other heritage benefits which stood to be weighed in the balance
together with the other public benefits.
31)
Historic England had been involved in other a
year of discussion and were confident when they said that the college had
acknowledged the benefits of removing the basement and glazing from the court
and the architectural merits of the current scheme. With this in mind, they
did not wish to object to the application.
32)
Historic England also welcomed the revisions introduced
to the scheme and retained its position of no objection.
33)
It was acknowledged that Victorian Society had
found some harm as they had concentrated on the 19th Century Bodley
Library rather than the wider college.
It was felt that they had not considered the wider heritage benefits.
Clarification had been sought on some of their comments to which they replied
that their committee did not consider this to be an overly contentious design, rather
that small adaptations could be implemented to mitigate any outstanding harm.
34)
The college had been consistent in that it did
not identify harm to the setting of the Bodley and indeed had recognised many
other heritage and public benefits from the proposal. Historic England did not object nor did the
conservation officer.
35)
If the Council concluded that there was any
residual heritage harm, then that weight stood to be weighed against the other
public benefits.
36)
It must be remembered that public benefits are
those that are included in the National Planning Policy Framework paragraph 8
which was anything which delivered economic social and environmental
objectives. The enhanced design and
streetscape improvements would be a definite positive, so would the
sustainability benefits as well as the economic benefits of delivering the
scheme and the improved accessibility to the library and the existing parts of
the historic building.
37)
The objection to optimum viable use was note
mentioned in the application. However,
the college contended that the new library would be better that the old one as
it would be accessible in a way that the old one was not. The CLAG website talked of phantom
benefits. The college thought that by
allowing its students with mobility issues and neurodiversity challenges to
study was a plus.
38)
A lot had been made in regard
to the massing of Christs Lane which the college disputed and that
having quite high buildings with a narrow lane between them was a feature of
the Cambridge vernacular. The lane would
be cool and would not be narrower and light from the upper stories would
increase the light in Christs Lane after construction.
39)
The building was on the north side of Christs
Lane and would not affect the light.
40)
The last contention was that the college and
officers had failed to bring to the Councils attention significant other plans including
the Mather design which had been dealt with significantly. The second was to create a streets schema
which was a single page that showed one elevation onto Christs Lane. The only advantage of this to the colleges
opponents was that it was shorter. It
also had no back elevation, so that the relationship with the Grade One listed
building was absent nor did it have any floorplans. Therefore, it was not at all certain that the
college could achieve what it needed inside the building and was not a serious
alternative. The Council were invited to
look at it and reject it as a consequence.
41)
In respect of the Massing, if the Council
allowed the college to build, it would still be the case that the more massive
and taller building on Christs Lane was already there. A new building would be smaller than the
building opposite and have the incidental advantage of protecting the colleges students
from the direct view from the penthouse floor of Christs Lane into their rooms.
42)
The scheme was all about the students, it was
not commercial and the college would not make money out of it. It was for the colleges 700 students over
generations. It was hoped that the
proposed building would last over 200 years so that many thousands of students
would benefit from a beautiful, varied building.
Case by Petitioners in Objection
43) The
Petitioners introduced their presentation.
44) It
was highly irregular for the Council to make a decision
on a subject that was still current to High court proceedings. Furthermore, it would open
up the Council to further challenge on the basis that a decision to
grant would give the impression of the Council bending over improperly to
support the interests of a private applicant that was frankly attempting to
circumvent proper process.
45) It
was presumptuous of the college to simply resubmit the same application effectively
saying to the Council you must try harder.
46) Whilst
the Court eventual position was unknown, a judge had already found evidence of
the previous recommendation for approval being defective on four accounts. It was very likely that the only way forward
would be found to be with a different or amended scheme.
47) Informed
opinion against the current scheme had hardened. Historic England had reiterated its view that
the development would cause harm. The Victorian
Society and the Councils own conservation officer had also hardened their
positions and Cambridge, Past, Present & Future had now objected in strong
terms.
48) This
all pointed to the proper course of action to defer any decision on the
resubmitted application.
49) The
petitioners did not characterise themselves as opponents and that there wanted
to collectively arrive at a solution that did not harm the city but satisfied
the objection and objectives of the college.
At no point were they trying to thwart the
objectives of the college. They
supported libraries and Christ College having a library. However, the design had been found to cause
heritage harm by every single independent expert, by statutory consultants,
public amenity societies, and the local civic body in Cambridge.
50) The
petitioners wanted to reconcile what would be a possible way of moving forward
that satisfied the colleges objectives whilst also not causing heritage harm.
51) It
was important to note that there was an intermediate step that kept being
skipped over every time there was a discussion.
A JR was brought because it was felt that Members had not been correctly
informed on the heritage aspects that needed to be taken into
account. The judge gave the
petitioners permission and the college, and the Council signed consenting to
quash the decision which has not been mentioned as all four grounds both had
agreed that there were errors and that the first permission should quashed.
52) It
was important to note that judge at the Planning Court stated that these issues
had a bearing on key planning considerations which informed the grant of
consent. This meant that the errors that
were made informed the permission granted.
When these errors are corrected there may be a different decision and
outcome.
53) It
was noting that neither the college or the Council
were defending the first permission.
Therefore, CLAG found it interesting that an identical application had
been submitted although the first permission had been quashed.
54) It
was anticipated that the judge at the hearing scheduled for 20 October 2026
would explain what had gone wrong and what needed to be corrected. CLAG had made the case so that the public
would benefit.
55) The
four grounds had all been conceded by the college and the Council and that the
Planning Committee had been misled.
These were:
·
Historic England found harm: Excessive bulk, too
big for its location. Members were told
the opposite.
·
The report found harm, then called
“neutral”. Both cannot be true. The balance never happened.
·
The library was counted as its own benefit,
securing optimum viable use erroneously.
A phantom benefit as it already has a library.
·
When heritage harm was found, less harmful
alternatives must be considered. Members
were actively dissuaded from considering alternatives on the table.
56) CLAG
quoted all of the heritage experts that had been
consulted all of which had found harm in the application. Members had been told that the heritage
benefits outweighed heritage harm.
57) Cambridge
Past, Present & Future noted the objections from residents of Christs Lane
and had found harm across multiple assets and found that the public benefits
did not outweigh the heritage harm.
58) It
was stated that the college was in opposition to every single heritage body
that had been appointed nationally.
59) It
was noted that the JR was not about the building but about the scheme with
heritage harm being denied outright. The
college could have adjusted the scheme, taken expert advice, waited for the
High Court’s reasoned judgement but instead had rushed to resubmit the scheme
unchanged.
60) It
was not clear to CLAG what the rush was to approve the application even though
the judge had refused the colleges request for special expedition.
61) The
current proposed structure did have a have a half basement which would require
digging and would be half a storey below ground. The building would also be larger than those
surrounding it.
62) A
previous design from 2010 had been rejected by the college as it would
compromise views from First Court and dwarf Christs Lane.
63) As
the first application was found to be of neutral harm it was felt that members
had again been misled. Members should
have been asked if the public benefits outweighed any harm. Planning balance would need to be weighed
differently going forward.
64) The
basement question was one of degree as it was half a basement.
65) A
building that deferred to the Bodley was preferred by the public.
66) The
colleges own Master Plan from 2023 had a library in the current location which
was more modest but had additional locations throughout the college. This was adopted and those locations are
currently being used by students. CLAG felt
that this was another alternative to the proposed application and should not be
disregarded.
67) CLAG
saw this as an opportunity. However,
under the current scheme the public would only get a bench, a gate but would
only get a “beautiful wall”. The wall
would be 14 m in height on a 6m wide lane.
This represented an enclosure 2.3 to 1.
The comparative streets mentioned by the college (including Trinity St)
were not pedestrian streets, and did not have vehicular access, nor were they key
thoroughfares in the city.
68) The
proposal would be over 40% more enclosed than the tightest of Cambridge streets
and would create a Canyon Effect.
69) Christs
Lane was a civic space and had an ecosystem sor society, economy and culture
and served a broad range of people.
70) The
Council had done an amazing job of redeveloping Bradwell’s Court which opened up the street for many people to use
and the Council needed to preserve this in Christs Lane.
71) This
was an opportunity for the Council, the College and the public. The application should be deferred and use
the next twelve weeks to look at a consented design, constellation and an
appropriately sized scheme and also bring all parties
together in an engaged, respectful, transparent and collaborative process.
Case Officer’s Comment
72)
Copies of the consultation response from all of the relevant heritage consultees had been distributed
to Members.
73)
The application at Christs College on St. Andrews
Street and proposed the demolition of the existing 1970s library, its
replacement, social and study spaces including the reprovision of a bridge to
the Bodley Library, alterations to the kitchen, upper hall and adjacent areas
including new plant, access improvements, alterations to toilets, provisions in
the south east range of Second Court, landscaping, ancillary works and the
installation of a temporary kitchen and dinning
facility in Second Court.
74)
The proposed development was to the southeastern
corner of Christs College site.
75)
The primary heritage points were the entirety of
the entrance court surrounding First Court which was Grade One listed.
76)
The relevant planning history was outlined.
77)
At the time of writing the presentation the
following comments had been received; there had been a total of108 comments of
which 61 were in support and 47 in objection with approximately 19
representations received from the Christ’s Lane action Group.
78)
In regard to the consultation date, the initial notification
letters were sent out on 11 June to adjoining premises, additional notification
letters were sent to four further addresses along St Andrew’s Street and
Christ’s Lane, a further update letter was sent to all notified neighbours
clarifying that comments would be received up to 22 July, and that the expiry
date for comments on the public portal was updated to clarify the updated end
date on 22 July.
79)
Historic England were comfortable to reiterate
their position of no objection. However,
their comments had been appended to the previous application where it was
clearly stated that they had concerns regarding the scale and bulk of the
building and would result in a certain level of harm to the significance of the
Grade One listed Christ’s College buildings.
80)
In terms of the internal Conservation Officer,
they had concluded that on balance the harm to the setting of the Grade One
listed building was considered to be less than
substantial at the lower end of the scale in requiring paragraph 215 of the
MPPF to be engaged. There were other heritage benefits considered but not sufficient
to outweigh the heritage harm.
81)
The Victorian Society had stated that the
proposal would result in a low to moderate level of less than substantial harm.
Case by Ward Councillors
Cambridge City Councillor Bick spoke as a ward councillor
and made
the following points:
82)
If the fundamental physical proposal was the same
as previously, he would choose to focus on that and wait to see what the
Planning Committee made of those changes to it
decision criteria.
83)
Given the opportunity he would return to the
points that he made previously with the concern primarily being the impact on
Christ’s Lane as public realm.
84)
The current frontage of the college onto Christs
Lane is extremely ugly looking like the back of an industrial estate. The
proposed plans could be argued to be an improvement. However, they were taller.
85)
In respect of the height, it sounded necessary
that the light and shade analysis be presented to the Planning Committee as
this had been challenged.
86)
There was a desire for a more active frontage
even more than that which had been proposed as at pedestrian level it was still
just a wall and enquired what options had been considered in the context of the
current scheme to improve the experience of the public real?
Members’ Questions and Comments
87)
Enquired what other options had been considered to
improve the pubic realm.
88)
If no decision was to be made, what was the
reason for holding this meeting.
89)
What was the harm in Planning terms and at what
level.
90)
There had been several quotes taken out of
context
91)
The public benefit needed to be refined
92)
The DCF could flag up any issues. However, clarity was needed on the height of
the chimneys and detail of the wall and the public benefit needed to be
defined.
93)
The existing library already had a partial
basement.
94)
Has the College considered public access to the
library.
95)
What was the justification for demolition and
could the existing building be revamped.
96)
Any heritage harm evidenced had to be balanced.
97)
Would the proposals create a canyon effect.
98)
Is the land in the proposal in the ownership of
the applicant.
99)
Would the new basement be at the same level as
the existing building.
100)Could the college be opened up in a more equitable way.
Summing up by the Applicant
101)The green credentials of the
proposed building were substantial which was why the design included
chimneys. The height of these was to aid
ventilation and to avoid further digging into the ground. The heigh had also been cut back as much as
possible.
102)The library was a private
space, although certain areas of the college were open to the public who could
enjoy the Courts. The college would look
at how it could share its facilities in the future.
103)The current library was out
of commission and a replacement was needed as soon as
possible and was having a negative impact on students.
104)The proposal was a
beautiful building.
Summing up by the Petitioners
105)Alternatives needed to be
considered such as the Colleges own Master Plan.
106)CLAG were
not opposed to a new library.
107)The proposal could be lower
108)Students only used the
library for 26 weeks of the year.
109)The building was already
accessible.
110)Better alternatives were available
and the proposal did not need to have such an overwhelming mass causing an canyon effect.
111)Heritage will be lost.
112)The chimneys could start at
a lower level and there were better options available for ventilation which
emitted less carbon.
113)Christ’s Lane needed to
remain a diverse pedestrian street.
Summing up by the Chair
114)
The Chair noted the following:
i.
Notes of the Development Control Forum would be
made available to relevant parties, published on the council’s website and appended
to the Planning Officer’s report.
ii.
The Planning Case Officer should contact the
Applicant/Agent after the meeting to discuss the outcome of the meeting and to
follow up any further action that was necessary.
iii.
The Applicant would be encouraged to keep in
direct contact with the Petitioners and to seek their views on any proposed
amendments.
iv. The
Council would follow its normal neighbour notification procedures on any
amendments to the application.
v.
Application to be considered at a future Joint Development
Management Committee.
vi. Along
with other individuals who may have made representations on the application,
the Petitioners’ Representatives would be informed of the date of the meeting
at which the application is to be considered by Committee and of their public
speaking rights. The Committee report would be publicly available five clear
days before the Committee meeting.