Minutes:
The Committee
received an application for full planning permission, which was previously
deferred by Committee on 18 October 2023.
The application sought approval
for the demolition of 2,730 sqm (GIA) office building (use class E(g)(i)) and
erection of 13,096 sqm (GIA) of research and development accommodation (use
class E(g)(ii)), including ancillary accommodation broken down as follows:
i.
Office accommodation (4,648 sqm)
ii.
Laboratory space (4,388 sqm)
iii.
Café (161 sqm)
iv.
Ground floor car park incorporating 37 no. car parking spaces.
v.
Plant space (924 sqm)
vi.
304 cycle parking spaces
vii.
Access and circulation areas, engineering works and footpaths/cycleways
viii.
Drainage and servicing infrastructure, and
ix. Hard and soft landscaping.
The Principal Planner updated their report by referring to amendments
contained within the Amendment Sheet namely:
i.
The
correction of references within the officer report to the Joint Development
Control Committee the application was previously brought to should refer to the
18 October 2023 meeting and not the 21 October 2023.
ii.
The
Urban Design Officer and the Landscape Officer had responded with no objections
to the amended proposals.
iii.
Amendments
to the wording of conditions 35, 36 and 37
a.
Condition
35 - Grey water recycling scheme
No development above base course
shall take place until a scheme for grey water harvesting and recycling
has been submitted to and approved in writing by the Local Planning Authority.
The development shall be carried out and thereafter maintained strictly
in accordance with the approved details.
b.
Condition
36 - Rainwater recycling scheme
No development above base course
shall take place until a scheme for rain water harvesting and recycling
has been submitted to and approved in writing by the Local Planning Authority.
The development shall be carried out and thereafter maintained strictly
in accordance with the approved details.
c.
Condition
37 - Water efficiency
The development hereby approved shall not be used or occupied until evidence in the form of the BREEAM Wat01 water efficiency calculator has been submitted to and approved in writing by the Local Planning Authority. Such evidence shall demonstrate the achievement of no less than 5 Wat01 credits.
The development shall be carried out and thereafter maintained strictly in accordance with the agreed details set out within the BREEAM Wat01 water efficiency calculator.
Reason: To respond to the serious water stress facing the area and ensure that development makes efficient use of water and promotes the principles of sustainable construction (Cambridge Local Plan 2018 Policy 28 and the Greater Cambridge Sustainable Design and Construction SPD 2020)
Edward Joslin (Applicant) addressed the Committee in support of the
application.
The Principal Planner, Delivery Manager and the Principal Transport
Officer said the following in response to Members’ questions:
i.
The location of the crossing place at Carling Road
was indicative and would be agreed at the detailed design stage. A formal
crossing was proposed which was appropriate given traffic volumes.
ii.
Construction on the Greater Cambridge Partnership
(GCP) Greenway was expected to begin in March 2024. If the Greenway did not
come forward for some reason a formal crossing could still be constructed within
the existing road layout.
iii.
The south bound bus stop into the city on Milton
Road was an existing bus stop.
iv.
Officers did not foresee conflict arising between
cars and cyclists in the car park as there was clear visibility and both would
move cautiously in the area.
v.
Confirmed that the cycle routes into and through
the building were connected to enable good access.
vi.
In response to concerns about the loss of trees,
confirmed that the trees which were originally proposed to be removed (which
were in front of the building) were now going to be replaced. Also noted hedges
which were going to be retained and new hedges which were going to be planted.
vii.
Confirmed that an
additional condition could be added to ensure protection of tree roots in
relation to foundation design.
viii.
Confirmed that external
seating was proposed to the north of the development and that additional
seating was now proposed following the removal of the external bike storage.
ix.
In response to concerns
raised regarding the ‘urban heat island effect’ advised that there was no
specific planning policy which dealt with this. The external seating area was
located to the north of the development, which would have the early morning sun
but would not have the sun shining on it during the hottest part of the day.
The balconies would be shaded by the southern projecting lantern feature. There
would also be a green / brown roof. The Applicant had also undertaken modelling
regarding overheating of the building itself. The BREAAM specifications would
ensure energy efficiency around heat escaping from the building would be
covered by proposed planning conditions.
x.
The materials and colour
scheme was proposed to be secured through condition 33 which was detailed in
the officer’s report. The Committee could request that the colour of materials be
brought back to Committee for their consideration.
xi.
The Quality Panel had
reviewed the design of the building.
xii.
Suggested amending
condition 33 to include consideration of the urban heat island effect when
considering the choice of materials for the building.
xiii.
Planning condition 35
dealt with grey water recycling and was detailed on the Amendment Sheet.
xiv.
Planning condition 37
was appropriately worded in terms of the timing of information.
Following Member debate, the Delivery Manager offered the following
summary of the conditions and informatives that would
be annexed to the officer recommendation contained in paragraph i and ii on
page 18 of the officer report:
i.
Conditions 1-31 in the original officer report
(pages 73-87)
ii.
Conditions 32 and 34 in the officer addendum report
(page 23)
iii.
Conditions 35 to 37 as listed on the Amendment
Sheet
iv.
Informatives listed in the
original officer report (pages 87-89)
v.
An additional condition (38) regarding foundation
design for new and existing trees
vi.
An amendment to condition 33 as set out in the officer
addendum report (page 23) to include consideration of the urban heat island
effect.
The Committee:
Resolved (by 9 votes to 1) to grant the
application for planning permission in accordance with the Officer
recommendation, for the reasons set out in the Officer’s report, subject to:
i. Conditions 1-31 in the original officer report (pages 73-87)
ii. Conditions 32 and 34 in the officer addendum report (page 23)
iii. Conditions 35 to 37 as listed on the Amendment Sheet
iv. Informatives listed in the original officer report (pages 87-89)
v. An additional condition (38) regarding foundation design for new and existing trees
vi. An amendment to condition 33 as set out in the officer addendum report (page 23) to include consideration of the urban heat island effect.
vii. The prior completion of a Section 106 Agreement under the Town and Country Planning Act 1990 with delegated authority to officers to negotiate, secure and complete such an Agreement and any others considered appropriate and necessary to make the development acceptable in planning terms.