Council and democracy
Home > Council and Democracy > Agenda item
Minutes:
A Deed of Variation was submitted in October 2020 seeking to vary the
s106 agreement under s106A of the Town and Country Planning Act 1990.
The variation sought approval to agree the s278 prior to occupation of
the development but remove the requirement to complete the agreed works prior
to occupation.
The Interim Management Support Officer updated her report to amend a
typographical error: The s278 requires the works to be completed by 21/06/2020
21/06/2021.
Mr Kaddish (Applicant’s Agent) addressed the Committee in support of the
application.
Members made the following comments in response to the Officer’s
comments:
i.
Expressed concern that the junction work would not
be completed within the specified 15 week period.
ii.
Expressed concern the application would exacerbate
existing traffic issues.
iii.
Expressed concern that s278 agreements took time to
take into effect across the city.
iv.
All buildings could be fitted out and used in
theory. Queried the impact of this on the car parking space reduction strategy.
Would there be higher demand than supply? Or demand to keep spaces (not reduce
the number)?
In response to Members’ questions the Interim Management Support
Officer, the Assistant Director and Principal Transport Officer said the following:
i.
The application was brought to Committee because
there was no delegation for officers to deal with amendments to Section 106
Agreements.
ii.
The s106 agreement aimed to mitigate the impact of
traffic on the junction.
iii.
The
Applicant had done all they reasonably could over several years to progress
work. If work was delayed, Officers were confident that the County would manage
work appropriately.
iv.
There were severe financial penalties for the
developer if work was delayed, so they had no incentive to let the scheme
timetable overrun.
v.
The Deed of Variation was in place to ensure work
would continue just in case delays occurred.
vi.
The Developer’s Team had done all they reasonably
could to look at what pipes etc were under the road surface to avoid delays due
to the impact on cable infrastructure.
vii.
Work would be undertaken at night, so the road
could operate as normal during the day.
viii.
The traffic management agreement for the development
was signed off by the County Council. It did not cover the construction period.
Limited impact was anticipated as work was due to take place at night for
period of 15 weeks.
ix.
The first building occupier was not in place yet.
They would not move in until at least 21 March 2021. Low traffic levels were
expected as few people travelled in lockdown.
x.
Fitting
out of the building could occur under the current legal agreement. The
Applicant would be concerned if they could fit out the building but not occupy
it immediately.
xi.
Road
work could occur at the same time as building occupation, it was a
balance between allowing occupation to take place and having the road works
occurring at the same time.
xii.
The car
parking space reduction strategy was included in the s106 agreement which had
been signed off. This sought to neutralise the increase in car parking numbers
from this scheme. It would take time to implement and was not a short term
strategy. The timescale was set out in the s106 agreement.
xiii.
The variation of conditions would not lead to a
conflict between today’s proposed variation to the s106 agreement and the car
parking reduction strategy. They were two distinct parts of the s106 agreement.
The Legal Officer stated this was a variation to planning obligations,
not a condition. There was no appeal open to the Applicant if councillors
amended the s106 agreement.
The Committee:
Resolved (by 9
votes to 2) to grant the application to approve the Deed of
Variation as below:
i.
In clause 1.1 at the end of the definition of
“Milton Road Works” insert the following: “or such other improvement works as
may be agreed in writing between the First Owner and the County Council.”
ii.
Delete paragraph 2.1 of Schedule 1 and replace with
the following paragraph: “2.1 Unless otherwise agreed in writing between the
First Owner and the Councils not to Occupy the Development until a Highways
Agreement has been completed in connection with the carrying out of works in the
highway in order to implement the Milton Road Works.”
iii.
Delete paragraph 2.2 of Schedule 1.
Councillor Bradnam asked for her objection to the scheme to be recorded.
Supporting documents: