A Cambridge City Council website

Cambridge City Council

Council and democracy

Home > Council and Democracy > Decision register > Meeting attendance > Decision details > Agenda and minutes

Agenda and minutes

Venue: Committee Room 1 & 2, The Guildhall, Market Square, Cambridge, CB2 3QJ. View directions

Contact: Toni Birkin  Committee Manager

Items
No. Item

15/1/JDCC

Apologies

To receive any apologies for absence.

Minutes:

No apologies were received.

15/2/JDCC

Declarations of Interest

Members are asked to declare at this stage any interests that they may have in an item shown on this agenda. If any member of the Committee is unsure whether or not they should declare an interest on a particular matter, they should seek advice from the Head of Legal Services before the meeting.

Minutes:

Name

Item

Interest

Councillor Bygott

15/4/JDCC

Personal: Alumnus of University of Cambridge

Councillor de Lacey

15/4/JDCC

Personal: Alumnus of University of Cambridge

Councillor Kenney

15/4/JDCC

Personal: Alumnus of University of Cambridge

 

15/3/JDCC

Minutes

To confirm the minutes of the meeting held on 17th December 2014 as a correct record. (To follow)

Minutes:

The minutes of the meeting of the 17th December 2014 were approved and signed as a correct record.

15/4/JDCC

Lot 2, North West Cambridge 14/1722/REM pdf icon PDF 289 KB

Lot 2, North West Cambridge

Additional documents:

Minutes:

The Committee received a reserved matters application for ‘Lot 2’ located within land between Huntingdon Road, Madingley Road, and the M11, North West Cambridge.

 

The Senior Planning Officer presented the reserved matters application for 264 key worker units comprising 100 one bedroom units, 161 two bedroom units and 3 four bedroom units, 1,983sqm of commercial uses A1, A3 and A4, flexible social space and ancillary estate office, alongside car and cycle parking, landscaping, public realm, utilities and associated ancillary structures, pursuant to outline approval 13/1402/S73.

 

The Committee noted the updates published in the amendment sheet, including revised conditions:

 

Condition 1 – Minor alteration to trigger:

 

Prior to the commencement of development, except for any underground enabling works, of each individual building hereby approved and identified below samples of the materials to be used in the construction…

 

Condition 2 – Minor alteration to trigger:

 

Prior to the commencement of development, except for any underground enabling works, of each individual area of public and private realm approved and identified below samples of the materials…

 

Condition 11 - Revised plan number:

 

NWC1- TLA- LB- ZZZ- XX- DRG- LD- 0305

 

The Committee made the following comments in response to the report.

       i.          Discussion of the merits of the application design. Most Members welcomed it.

     ii.          Some wider discussion regarding Areas of Major Change and Green Belt Policy.

   iii.          The phasing of developments meant that appropriate commercial and residential infrastructure was implemented at an early stage with appropriate levels of housing.

   iv.          Restrictions on vehicle delivery times were welcomed.

    v.          The provision of key worker tied housing reduced some of the demand for affordable market housing. There was a recognised housing need for ‘post-docs’, to encourage them to come to Cambridge from around the world. Noted that the overarching strategy had been addressed at outline application stage.

 

In response to Members’ questions the Principal Planner and the Senior Planning Officer said the following:

       i.          The courtyard areas were secluded and semi-private in nature, so people from outside the development were unlikely to visit them as public open spaces. The areas were not gated, so people (ie non-residents) could walk through.

     ii.          62 cycle parking spaces were available for local centre visitors. An additional 84 were allocated for the food store (separate application). These would cater for different bike sizes.

   iii.          Some on-street car parking would be available in phase 1 of the development. Phase 1 had a Parking Strategy setting out allocated parking for key worker and market housing, plus visitors to these. Parking would be controlled by Traffic Regulation Orders in primary and secondary streets to prevent ‘fly parking’ by commuters.

   iv.          The Ridgeway cycle route ‘quality setts’ were designed to encourage cyclists to slow down in areas where the public realm would be shared with pedestrians, the surface material would not physically slow down cyclists.

    v.          Officers anticipated there would be sufficient retail outlets as part of the phase 1 development. The site only required complementary facilities, the food store was over and above the required provision.

   vi.          The rills were expected to be dry for most of the year. Species of plants for the development were chosen with this in mind.

 vii.          The University of Cambridge was responsible for managing rills to prevent them becoming clogged with litter. The University had a good public realm management record. Most rills were located in private areas. An informal request could be made to the University of Cambridge asking them to ensure the rills did not become clogged with litter, but this could not be made into a formal planning condition.

viii.          Public areas, access ways and courtyards were overlooked by buildings to discourage crime. There was provision in adjacent Lots 1 and 4 for youth and play facilities. S106 would trigger areas coming forward when sufficient housing was in place (youth and play facilities were already approved by JDCC).

   ix.          The Applicant had undertaken a letterbox study to ensure a majority of property letterboxes were accessible from the street. Deliveries could also be made to people’s front doors eg items ordered on-line.

    x.          The mix of housing for phase 1 was based on immediate key worker needs. Therefore most were 1-2 bedrooms, with a few 4 bedroom units in shared houses. 3-4 bedroom houses were expected as part of market house proposals in the remainder of phase 1.

   xi.          Key worker housing was only available to university staff who met eligibility criteria. This policy had been in place since 2003.

 

The Head of Planning Services noted Councillor’s concerns regarding tied housing, but reassured them issues had been considered at previous JDCC committees through the outline application and S106.

 

 xii.          The impact of building heights had been considered in the design to avoid the creation of wind tunnels.

xiii.          Public transport provision would change over time, but a Sunday bus service was expected. The Principal Planner undertook to check public transport facilities and inform JDCC Members.

 

The Committee:

 

Resolved (by 13 votes to 0 with 2 abstentions) to grant the reserved matters application in accordance with the officer recommendation, for the reasons set out in the officer report, and subject to the amended conditions recommended by the officers.

15/5/JDCC

Pre Application Briefing: Newmarket Road, Cambridge

Ice Rink Leisure Facility

 

Minutes:

The Committee received a presentation from the developer on the proposed Newmarket Road Ice Rink.

 

Members raised comments/questions as listed below. Answers were supplied, but as this was a pre-application presentation, none of the answers were to be regarded as binding and so are not included in the minutes.

 

1.    The ice rink was considered an interesting proposal. It could increase city amenities.

 

2.    The ice rink is proposed to be located on the Newmarket Road Park&Ride site. What would be the impact on car parking capacity at the Park&Ride site?

 

3.    Queried bus service provision to the ice rink, especially in the evenings. If this was limited, people may have to commute on foot or by car.

 

4.    Asked if there was sufficient parking capacity for event visitors, as well as sport competitors eg for teams and their supporters.

 

5.    Queried provision of coach parking and drop-off points.

 

6.    Queried building access point locations. Why was the entrance at the back of the building, away from drop-off points.

 

7.    Asked if the ice rink could still be located in Newmarket Road if the Park&Ride site were to move.

 

8.    Queried the impact of the proposed permanent ice rink on the temporary Christmas one.