Council and democracy
Home > Council and Democracy > Issue
39 Housing Planned Maintenance Contract - Progress Report PDF 70 KB
Minutes:
Matter for Decision
The Officer’s report provided details of works
delivered and performance achieved in the first year of the housing planned maintenance contract
that started in July 2011.
Decision of Executive Councillor for Housing
This report was for
information only.
Reason for the Decision
Not applicable.
Any
Alternative Options Considered and Rejected
Not applicable.
Scrutiny Considerations
The Committee
received a report from the Principal Surveyor regarding the Housing Planned Maintenance Contract Progress Report.
The Principal Surveyor updated his report to amend a typographical error.
Text in the table in paragraph 5 should state “134 Kitchens Bathrooms installed”.
In response to the
report the Committee expressed concern that tenant satisfaction figures did not
reflect comments made to Tenant and Leaseholder Representatives. It was
suggested that comments would be more objective if the Resident Liaison Officer
(RLO) was seen as independent, instead of affiliated to a contractor.
In response to
Members’ questions the Head of Estates & Facilities, Asset Manager plus
Principal Surveyor confirmed the following:
(i)
Customer
satisfaction data was collected by a RLO. A surveyor would check work tasks
were completed then the contractor’s RLO would invite feedback from tenants.
Feedback forms were completed by tenants.
(ii)
If tenants had
concerns regarding contractor’s work, these could be raised with Council
Officers.
(iii)
Officers
looked at overall trend information in feedback forms. There was no specific
cut off point between satisfied and unsatisfied scores. Tenants were asked to
mark their views on a scale of one to ten, one being unsatisfied and ten being
satisfied.
(iv)
The Director of Customer & Community Services said
Officers would undertake to review the methodology of tenant satisfaction data
collection and report back to HMB. This would include initial satisfaction
surveys, and any follow up feedback in case issues arose some time after work
had been completed.
(v)
Apollo’s contractual costs
exceed predicted costs by 10%. The Council would claw back the majority of
this.
(vi)
No void properties were
subject to sulphate issues in the reporting year covered by the Principal Surveyor’s progress report. The
Council preferred to undertake remedial work for sulphate issues on void
properties, but would undertake work on occupied properties too if required.
Sulphate issues were scrutinised as part of the assessment criteria when the
Council acquired new properties.
(vii)
Apollo had not
met all of its contractual obligations regarding waste management and adding
social value (work placements), as work had started late (mainly undertaken in
the second half of this reporting year). This was due to staff TUPE condition
issues. The Council was monitoring the situation.
(viii)
The Council
had a supply chain link to contractors to select best value products to address
its maintenance needs. The Council could not specify individual branded
products to use, but specify standards/requirements it expected products to
satisfy. Officer’s have extensive contract specification writing expertise. The
Council has a seven year cyclical programme to cover all maintenance issues,
instead of subdividing these into fencing, boilers etc.
(ix)
It was part of
the Council’s role to monitor contractor’s health and safety practices.
Officers would raise any issues they witness (eg through unannounced visits)
with contractors.
(x)
The Principal Surveyor undertook to liaise with Councillor
Blencowe post HMB regarding construction skills certification scheme card requirements.
(xi)
Tenant
handbooks could be updated to list property specifications in future.
The Committee noted
the report, but were not required to endorse any recommendations.
Conflicts of Interest Declared by the Executive Councillor (and any
Dispensations Granted)
Not applicable.