Council and democracy
Home > Council and Democracy > Issue
Minutes:
The Committee received a report from Network Rail Officers regarding the Ely Area Catchment Enhancement
project, which was a scheme to increase both freight and passenger services which
run through the Ely area. Officers also spoke to the project in relation to the
Fen Road crossing. Network Rail’s presentation slides could be found via the
meeting webpage: Agenda
for North Area Committee on Thursday, 18th November, 2021, 6.30 pm - Cambridge
Council
In response to Members’ questions Network Rail Representatives’ said the
following:
i.
Network
Rail had been exploring future proofing the capacity of the rail junction. Ely
was a bottleneck for trains and was a challenge to overcome. The Department for
Transport had asked Network Rail to look at increasing the capacity through Ely
to 10 trains per hour, Network Rail was looking at capacity above that. The
preliminary results suggested that Network Rail could deliver more capacity
than the Department for Transport asked for, however there would be other
constraints on the network which would need to be addressed.
ii.
Was
aware that Fen Road was the only vehicular access to houses that side of the
railway line and understood residents’ concerns and frustrations regarding the
length of time the barriers were down. Should an emergency vehicle be waiting
at the level crossing, the Signaller should see this via the CCTV and can take
a decision to help the vehicle cross the crossing quicker. Network Rail had
explored what could be done to reduce barrier downtime. All technical solutions
had been explored to reduce the barrier downtime. There were no technical
solutions to reduce the barrier downtime.
iii.
There
was a wider issue, Network Rail officers had presented the options available
regarding the Ely Area Catchment Enhancement scheme. Other work had been
undertaken to make sure that they were minimising the length of time the
barrier was down.
iv. Network Rail responded
to the North East Cambridge Area Action Plan (NECAAP) and said that land should
be reserved to facilitate connections. Thought some of the plans involved a
foot crossing near the level crossing. Would be willing to work with third
parties. Would discuss issues raised with colleagues. Network Rail’s comment on the NECAAP
consultation was not a commitment, the comment said land should be set aside.
v.
The
Fen Road crossing was a complex issue. Network Rail were not saying that it was
for other parties to solve problems for Network Rail. In an ideal world would
want to close level crossings as they were a risky structure to have on the
rail network because of the interface with members of the public however they
needed to have a credible alternative available to be able to close a level
crossing. The issue was the availability of land where alternative access could
be provided and to understand what options were available and whether Highways
would adopt any such land.
Action: Network Rail agreed to discuss with the Councils (in response to
request from Cllr Bird and Cllr Hawkins (SCDC)) regarding Fen Road crossing /
alternative road / bridge.
Members of the public asked a number of questions, as set out below.
1. What steps were being taken to lessen the time
that the Fen Road Level Crossing was down, waiting for trains to leave
Cambridge North station heading south, for most of which time the trains were
still sitting in the station.
Network Rail response: All technical solutions had been explored to reduce the
barrier downtime. There were no technical solutions to reduce the barrier
downtime
2. The problem was less the
total down time but the length of individual down times which causes
frustration. This had got better, but
can still be a problem. When the barriers were down for 1
minute, this was not too much of a problem,
8 minutes plus was very frustrating. Asked if there were any incidents or
risk factors, or a threshold for closure of the Fen Road Crossing. Felt the danger from Fen Road Crossing was less from train accidents than road
accidents arising from drivers’ frustration.
Network Rail response: The safety of level crossings was
regularly reviewed, the frequency of reviews depended on a number of factors
including accidents or near misses.