Council and democracy
Home > Council and Democracy > Issue
Greater Cambridge Partnership (GCP) Fen Road update on the schedule of works
Minutes:
The Committee received a verbal update on the Fen Road Chisholm Trail
project.
The update outlined:
i.
The project had had some key milestones over the
last 9 months, including the safe delivery of the underpass on Newmarket Road.
ii. The Common project
was to be completed in the next 3-4 weeks.
iii.
The programme would then move on to Fen Road and
where pedestrians and cyclists would leave the new Chisholm Trail. A safety
critical area had been identified, where visibility lines would be challenging
coming on to Fen Road. Experts had been consulted to make this area as safe as
was possible.
iv.
Consultations with councillors had taken place.
v. It was hoped the
entire project could be completed by the end of the year.
vi.
The design of the crossing sought to ensure full
visibility of pedestrians and cyclists on Fen Road.
The Committee made the following comments in response to the report:
i.
Expressed concerns about the way people would leave
the Chisholm Trail and come on to Fen Road. Would have liked to have seen a
traffic light / crossing light but was aware of the costs of this. Asked for a
review of the crossing 3 - 4months after the crossing was opened.
ii.
Was grateful to the Greater Cambridge Partnership
(GCP) for delivering this project but noted that there was a bigger problem at
this area. Would like to have seen a crossing but noted the advice from
officers. Asked to see the post road opening safety audit data as this might
provide evidence for other issues further along Fen Road. Asked to see the
detailed specification for the crossing.
iii.
Felt that not all of Cambridgeshire observed the
road hierarchy particularly on Fen Road.Â
iv.
Hoped there would be barriers around the chicanes
to prevent drivers driving over the raised part of the chicanes.
v.
Asked if there would be a give way sign.
vi.
Noted that an alternative proposal had been ignored
(vehicle access to East Chesterton end from the north of Milton Road).
The GCP Project Officer said the following in response to Members’
questions:
i.
Costs were only one of the factors against a
signalised system. The locality of the rail line was another factor. There were
concerns about traffic stacking if a signalised system was put in place.
Confirmed a post road opening safety audit would be carried out.
ii.
Physical obstructions at the crossing should deter people
from driving at speed. The chicanes also shortened the distance of the crossing
making it quicker and safer for people to cross.
iii.
Confirmed there would be robust bollards on the
approach to the crossing to ensure vehicles were directed into the correct
position.
iv.
Confirmed there would be clear highway signage for
all road users.