41 Estates & Facilities Compliance Data PDF 286 KB
Additional documents:
Minutes:
This item was
Chaired by Diana Minns (Vice-Chair)
Matter for
Decision
The report provided an
update on the compliance related activities delivered within the Estates &
Facilities Team, including a summary on gas servicing, electrical testing and
fire safety work.
Decision
of Executive Councillor for Housing
i.
Noted current position of the Council regarding Compliance,
and the progress of ongoing associated works.
Reason for the Decision
As set out in the Officer’s report.
Any Alternative Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee received a report from the Interim Risk and Compliance Manager.
The Interim Risk and Compliance Manager and Director of Neighbourhoods
and Communities said the following in response to Members’ questions:
i.
The asbestos register included garages as it
covered solid structures.
ii.
Would follow up whether the emergency lighting had
been fixed.
iii.
Had requested the Internal Audit Team considered
potential for learning in relation to the gas safety issues, with a report
coming back to this committee when that work is completed.
iv.
Future reports would include an update on Hanover
and Princess Courts and Kingsway until works had been completed.
v.
Nobody would be left without heating for their home.
If tenants had gas central heating, the proposal was to change them to electric
central heating. 19 homes to date had been capped off.
The Committee unanimously resolved to endorse the recommendation.
The Executive Councillor
approved the recommendation.
Conflicts of Interest Declared by the Executive Councillor (and any
Dispensations Granted)