34 Environmental Improvement Programme PDF 273 KB
Report to follow
Additional documents:
Minutes:
The Committee received a report from the Public Realm &
Project Delivery Team Leader regarding the Environmental Improvement Programme
(EIP). The report outlined changes to the EIP during 2018/19 and reviewed the
latest round of applications within East Area.
The Committee were asked to recommend the following:
i.
Note
the operating amendments to the programme agreed by the Executive Councillor
for Streets and Open Spaces following Environment and Community Scrutiny on 21
March 2019
ii.
Note
the allocation of funding to continue with a programme across all areas for the
period 2019-21.
iii.
Consider
the allocation of £10,890 from local area EIP funds in 2019/ 20 towards the
provision of 66 summer hanging baskets along Mill Road.
iv.
Consider
new project aspirations received in the latest 2019/ 20 round for funding from
new central strategic, and local area, EIP allocations
v.
Identify
those East area priorities to be recommended to the Executive Councillor for
Streets and Open Spaces for funding from the central, strategic, EIP
allocation.
vi.
Support
those projects selected for implementation, subject to them being viable,
obtaining consents as necessary, positive consultation and final approval by
the Council’s Place Board, Ward and Executive Councillors, where required.
In response to questions and comments the Public Realm
Engineering & Project Delivery Team Leader said the following:
i.
There was currently over £28,000 new funding
available for area led projects for this year; with a small remainder of
funding from the previous year which should take the total to £35,000
approximately.
ii.
Suggested that only half the projects put
forward would be affordable.
iii.
Confirmed there would be scope for discussion
with the County Council regarding the strategic funding for verges and the
County funding for footpaths.
iv.
The project (Romsey Planters) submitted by
Councillor Baigent was not on the list in the report as officers did not
consider it to be a viable and a deliverable project at this stage. Further
work would be required to determine the scale and the cost to ask the Committee
to prioritise funding.
v.
Any schemes not selected might be considered the
following year, subject to annual budget setting.
vi.
Agreed to the Committee’s request for an
assessment of those projects that did not make the list which could be
circulated at a later date.
vii.
Noted the request to remove E12 (Petersfield
Green planting beds and benches) from the list for consideration.
viii.
The cost for providing hanging baskets for 2019
had already been incurred funded in 2018, subject to area committee approval
the cost could be met by the Environmental Improvement Programme via a recharge
if the Committee agreed; this would reduce the funding available for further
schemes.
ix.
Might be possible to put forward funding for the
hanging baskets for 2020 and not a recharge.
x.
To install the hanging baskets, the cost of the
access platform and licence was considerable. There was also the cost of the
servicing, though the cost would fluctuate dependent on the weather. Efforts
had been made in recent years to conserve water through the type of baskets
that had been purchased.
The Committee:
Resolved unanimously
to:
i.
Support the following from the strategic
funding:
·
E6: Whitehill
Road verge protection, £10,000.
·
E9:
Coleridge streets tree and verge protection, £10,000.
Resolved unanimously
to
ii.
Resolved
unanimously to allocate from the local area EIP fund to:
·
E1: Barnwell
Road library beds planting, £2,000
·
E3: Dudley
Road Recreation Ground addition of benches,
£3,000.
·
E8: Birdwood
Road bus shelter, £10,000.
·
E10: Petersfield ward streets window boxes,
reduced from £10,000 to £7,000.
·
E11: North
Petersfield noticeboards, £3,000.
·
E14: Romsey
‘insect hotels’, £2,000
iii.
Resolved to
allocate from the local area EIP funds:
·
£3000 towards the recharge for the provision of
66 summer hanging baskets along Mill Road in 2019/20.
iv.
Resolved
to allocate from the local area EIP funds;
·
£3000 to the suggested Romsey Planters project
following further investigation work by officers if financially viable.
·
E10: Petersfield ward streets window boxes
(£3,000 to top the full amount to £10,000 if available).
v.
Resolved to
allocate in reserve from the strategic funding:
·
E5: Wadloes Road verge planting, £8,000
·
E13: Gilsson
Road (trees and tree pits (top up existing scheme), £5,000