10 New Social Housing – Colville Road 2 PDF 963 KB
Minutes:
This item was Chaired by Councillor
Todd-Jones
Matter for Decision
The report sought approval for a capital budget for the scheme based on the indicative capacity study which has been undertaken for the site and the outline appraisals referenced in this report and for the delivery route to be adopted.
Decision
of Executive Councillor for Housing
i.
Approved
that the scheme was brought forward with an indicative capital budget
for the scheme of £13,781,590 to cover all of the site assembly, construction costs,
professional fees and associated other fees to deliver
a scheme that meets an identified housing need in Cambridge City.
ii.
Authorise the Strategic Director in consultation
with the Executive Councillor for Housing to approve variations to the scheme
including the number of units and mix of property types and sizes outlined in
this report.
iii.
Approved
that the site was offered to CIP to progress in accordance with the CIP process
which was approved at Strategy & Resources Committee on 9th
October 2017 subject to a value for money assessment to be carried out on
behalf of the Council prior to entering into the Agreement for Lease set out in
that process.
iv.
Delegated authority to the Strategic Director to
commence Compulsory Purchase Order (CPO) proceedings on Leasehold properties to
be demolished to enable the development should these be required.
v.
Delegated authority to the Strategic Director to
serve initial Demolition Notices under the Housing Act 1985.
Reason for the Decision
As set out in the Officer’s report.
Any Alternative Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee received a report from the Manager, Housing Development Agency.
The Committee welcomed the scheme.
The Committee resolved (by 4
votes to 0) to endorse the recommendation.
The Executive Councillor
approved the recommendation.