Minutes:
This item was Chaired by Councillor Mike Todd-Jones
Matter for Decision
The report sought approval for the conversion of Ditchburn Place day centre into 2No. one bedroom self-contained sheltered accommodation flats. The 2 units would be in addition to the current 51 unit refurbishment of Ditchburn Place. The report also requested approval for a capital budget for the HRA and Devolution grant expenditure covering costs for their conversion.
Decision
of Executive Councilor for Housing
i.
Approved
inclusion of a capital budget of £125,000 to meet the land acquisition costs,
recognising the transaction was carried out under delegated authority earlier
in 2018/19.
ii.
Approved
the indicative capital budget for the conversion of £207,000 to cover all of
the construction costs, professional fees and associated fees to deliver the
extra units.
iii.
Approved
the addition of the works to create the 2 units to the existing build contract
with Cocksedge Building Contractors Ltd. This contractor was currently on site
working on the larger refurbishment scheme.
Reason for the Decision
As set out in the Officer’s report.
Any Alternative Options Considered and Rejected
Not applicable.
Scrutiny Considerations
The Committee received a report from the Development Manager, Housing Development
Agency.
The Committee unanimously
resolved to endorse the recommendations.
The Executive Councillor for Housing approved the recommendations.