40 S106 Area Corridor Schemes PDF 43 KB
Feedback
on proposed S106 Area Corridor Schemes, to inform a decision on which schemes
should be recommended to the County Councils Committee.
Minutes:
The Capital and Funding Manager introduced
the item as per the agenda.
1.
Martin Lucas-Smith
stated that the Eastern Gate encompassed a lot of work. He asked if the
Newmarket Road / Elizabeth Way roundabout could be given priority.
Councillor Johnson confirmed that an Eastern
Gate framework was being developed. A feasibility study was planned to
establish what could be achieved.
Councillor Herbert asked for detailed
information on deadlines. He requested a clear set of expected completions
dates for the delivery of projects already in the pipeline.
Councillor Roberts asked for an update on
the Chisholm Bridge. A previous meeting of the Committee had sent a request to
the North Area Committee for a contribution. Councillor Blencowe undertook to
raise this matter and the next Area Chairs meeting.
Action Councillor Blencowe
Councillor Owers
requested an update on the Leisure Park link bridge. The Capital and Funding
Manager confirmed that this had been delayed by legal difficulties.
Councillor Smart suggested that Sainbury’s be approached for a contribution towards the
trial of an orbital bus route from the Marshall’s site to Addenbrooke’s
Hospital. Concerns were raised that the proposed new bus route would impact on
the existing 114 services. Councillor Bourke was concerned that this bus route,
which serves vulnerable communities, might suffer cuts. However, other members
suggested there was room for both services and that Abbey
residents had raised a 1,000 signature petition in support of a direct
route to the hospital.
Further details were requested on the
entrance to Stourbridge Common proposals and the high figure suggested for this
was questioned. The Capital and Funding Manager confirmed that the any
underspend on the project would be returned to the pot for reallocation.
The timetable for delivery of an extension
to the Tenison Road scheme was questioned. Officers confirmed that Tenison Road
was to be regarded as a design template that could be replicated quickly in
surrounding areas.
2.
Hester Wells stated
that given that the consultation on the first stage of Tenison Road had yet to
open it was too soon to consider funding extensions to the project.
The Committee noted her comments.
Councillor Bourke asked if Eastern Corridor
funding could be used for projects in Mill Road. Officers confirmed that this
would be possible. The Capital and Funding Manager suggested that a meeting be
arranged with members to discuss proposals. In addition, a budget allocation
would be needed to allow scoping work and feasibility studies of any proposals
to be completed.
Councillor Herbert reminded the Committee
that additional funding might also be forthcoming from the City Deal.
Resolved
(unanimously)
The following four projects were approved
from existing budgets:
5.1 Entrance to Stourbridge Common (£50,000)
5.2 Chisholm Trail (Bridge) (£50,000)
5.4 Bus Service from Newmarket Park and Ride
to Addenbrooke’s Hospital (£95,000) (subject to
negotiations with Marshall’s)
Funding to allow scoping work of Mill Road
Projects (£20,000)
The following project was earmarked for
approval in the future when funding becomes available.
5.3 Additional funding for Tenison Road (£500,000)