To approve new build housing (estate regeneration) scheme at Colville Road. This is the third scheme in this area and is adjacent to the previous two.
The scheme requires a capital budget to progress up to planning application
stage and approval to commence consultation with tenants, leaseholders and
commercial tenants.
Matter for
Decision
The report seeks approval of a capital budget for the
scheme, based on the indicative capacity study which has been undertaken for
the site and the outline appraisals referenced in this report, and for the
delivery route to be adopted
Decision
of Executive Councillor for Housing
i.
Approved that the scheme be brought forward with
an indicative capital budget of £11,103,200 to cover all site assembly,
construction costs, professional fees and further associated fees, to deliver a
scheme which meets the identified housing need in Cambridge City.
ii.
Authorised the Strategic Director in
consultation with the Executive Councillor for housing to approve variations to
the scheme including the number of units and mix of property types and sizes
outlined in this report.
iii.
Approved that, subject to Council approval of
the budget, delegated authority be given
to the Executive Cllr for Housing in conjunction with the Strategic Director to
enable the site to be developed through Cambridge Investment Partnership (CIP)
subject to a value for money assessment to be carried out on behalf of the
Council.
iv.
Delegated authority to the Strategic Director to
commence Compulsory Purchase Order (CPO) proceedings on Leasehold properties to
be demolished to enable the development, should these be required.
v.
Delegated authority to the Strategic Director to
serve initial Demolition Notices under the Housing Act 1985.
vi.
Approved a delegation to the Section 151
Officer, in consultation with the Executive Councillor for Strategy and
Resources and the Executive Councillor for Housing, to approve the most
appropriate valuation basis, funding route and accounting treatment for the
value of the commercial units being provided as part of the development of
Colville 3.
Reason for the Decision
As set out in the
Officer’s report.
Any Alternative Options
Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee
received a report from the Head of Housing
Development Agency.
Cherry Hinton Ward Councillor Dryden commented:
i.
Supported the scheme and asked for a meeting to be
held with residents, particularly those whose homes were set to be demolished
if the recommendations were approved. Noted that officers had held meetings
with some of the businesses.
Cherry Hinton Ward Councillor Ashton commented:
i.
Thanked officers for their work on the project. Was
pleased that the development was solely for council housing and was not going
to be sold off for private development.
Expressed concerns on behalf of existing tenants about where they would
be moved to during the construction phase.
ii.
Shops were used in Cherry Hinton, there were no
vacant shop units on the High Street. Residents had expressed their concerns
about what would happen to them and he noted there were opportunities for the
shops to be relocated within Cherry Hinton. Asked for consideration to be given
to locating temporary portacabins on open space to keep local businesses in
Cherry Hinton.
The Committee made the following comments in response to the report:
i.
Referred to page 290 of the agenda and noted that
the council was still not aiming for net zero carbon development.
The Head of Housing Development Agency said the following
in response to Members’ questions:
i.
Subject to the decision of the committee and
Executive Councillor, meetings could be arranged with residents and
consideration would be given to the most appropriate way to re-house residents
affected by the development.
ii.
Officers had been working with colleagues in Property
Services and consideration would be given to temporary facilities for
businesses to use.
The Committee resolved by 5 votes to 0 to endorse the recommendations.
The Executive Councillor
approved the recommendations.
Conflicts of Interest
Declared by the Executive Councillor (and any Dispensations Granted)
No conflicts of interest
were declared by the Executive Councillor.
Publication date: 02/12/2020
Date of decision: 24/09/2020