Council and democracy
Home > Council and Democracy > Decision details
Decision Maker: Executive Councillor for Housing
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Approve a capital budget to redevelop Council sites at the Meadows Centre and Buchan Street for Council housing.
Public Speaker
Councillor Price addressed the Committee as follows:
i.
The proposal was an
exciting opportunity.
ii.
The Meadows Community
Centre had been an asset to the local community.
iii.
New development should be
even better.
iv.
The Buchan Street
development would provide much needed housing.
Matter for
Decision
The report proposed a redevelopment of The Meadows and
Buchan Street sites, to provide much-needed Council rented housing, and a new
community centre. It proposed adding these sites to the Council’s Rolling
Programme of Housing development, making the resources for the redevelopment
available, and working with centre users, neighbours, staff and others to
ensure the design of the new homes and community centre provides well for the
local community.
Decision of Executive
Councillor for
Communities:
i.
Approved
the rationalisation of two community centres into a new community hub in line
with the Community Centres Strategy (June 2017), in order to make land
available for much needed Council housing; The development process will ensure
that a community centre remains open throughout the redevelopment period; and
that local residents and centre users are engaged in the detailed design of the
new community facility.
Decision of
Executive Councillor for Housing:
i.
Approved
the addition of Meadows and Buchan Street sites to the Rolling Programme, to enable
detailed design and project work to proceed
ii.
Approved the
indicative mix of the proposed scheme, subject to design and planning, to
include a mix of Council rented housing, as set out below:
|
Meadows |
Buchan |
1B2P Flat (Housing First) |
|
2 |
2B4P Flat (Housing First) |
|
1 |
1B2P Flat |
58 |
6 |
2B4P Flat |
27 |
5 |
3B5P House |
0 |
7 |
Totals |
85 |
21 |
|
|
|
Community Centre
GIA |
1583m2 |
|
Retail space GIA |
|
148m2 |
iii.
Recommended
to Council the inclusion of an indicative budget of £26,379,880 in the Housing
Capital Programme (to be presented to Council in the HRA BSR).
iv.
Authorised the
Strategic Director, delegation exercised in consultation with the Executive
Councillor, Chair and Spokes following future business planning, to seek
approval from the Secretary of State for use of HRA resources to fund part of
the cost of the Community Centre and commercial unit (on the basis that this
would aid the release of land for much needed housing in line with national
government policy), subject to this being viable within a revised HRA business
plan, and to vary the contributions recommended from the Housing Revenue
Account and the General Fund in the light of the decision.
v.
Approved
that the site is offered to CIP to progress in accordance with the CIP process
which was approved at Strategy & Resources Committee on 9th October 2017
subject to a value for money assessment to be carried out on behalf of the
Council prior to entering into the Agreement for Lease set out in that process.
Reason for the Decision
As set out in the Officer’s report.
Any Alternative Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee received a report from the Manager, Housing Development Agency.
The Committee made the following comments in response to the report:
i.
Thanked officers for work over a number of years
that had brought this project to the point of delivery.
ii.
Expressed regret at the loss of green space.
iii.
Concerns were raised about conflicting demands for
parking and the level of provision for the new housing units.
The Manager, Housing Development Agency said the
following in response to Members’ questions:
i.
The new facility would be slightly larger than the
combined size of the two existing community facilities.
ii.
Stated that the remaining green space would require
better management to ensure the full benefit was achieved.
iii.
The proposed building would cross the City /South
Cambs boundary and planning permissions would need to take this into account.
iv.
Sports England was expected to approve the plans.
v.
Existing users would be given priority when
allocating resources in the new facility.
The Executive Councillor for Communities
confirmed that a range of consultations had taken place and the resulting
scheme was intended to meet as much need as possible.
Councillor Cantrill expressed concerns that
an application was being submitted to the Secretary of State regarding the use
of HRA funds for the community building when full business case had not been
completed. He asked for an assurance that this Committee would have sight of
the business case before such an application was submitted.
Councillor Cantrill proposed an amendment to delete
recommendation 2.2.4.
Authorise the Strategic
Director to seek approval from the Secretary of State for use of HRA resources
to fund part of the cost of the Community Centre and commercial unit (on the
basis that this would aid the release of land for much needed housing in line
with national government policy), subject to this being viable within a revised
HRA business plan, and to vary the contributions recommended from the Housing
Revenue Account and the General Fund in the light of the decision.
The Strategic Director suggested additional wording to
recommendation 2.2.4 could achieve the desired level of scrutiny.
Councillor Cantrill withdrew the proposed amendment to
delete recommendation 2.2.4 and proposed the following amended wording
(additional text in bold):
Authorise the Strategic Director,
subject
to final approval from the Housing Scrutiny Committee, to seek approval from the Secretary
of State for use of HRA resources to fund part of the cost of the Community
Centre and commercial unit (on the basis that this would aid the release of
land for much needed housing in line with national government policy), subject
to this being viable within a revised HRA business plan, and to vary the
contributions recommended from the Housing Revenue Account and the General Fund
in the light of the decision.
The amendment was lost by 3 votes to 4.
Following Committee discussions, the
following amendment to recommendation 2.2.4 was proposed:
Authorise the Strategic Director,
delegation
exercised in consultation with the Executive Councillor, Chair and Spokes
following future business planning, to seek approval from the Secretary of State for use of HRA
resources to fund part of the cost of the Community Centre and commercial unit
(on the basis that this would aid the release of land for much needed housing
in line with national government policy), subject to this being viable within a
revised HRA business plan, and to vary the contributions recommended from the
Housing Revenue Account and the General Fund in the light of the decision.
This amendment was carried by 4 votes to 0.
The Committee resolved (by 4
votes to 0) to endorse the recommendation 2.1.1.
The Executive Councillor
for Communities approved the recommendation.
The Committee resolved (by 4
votes to 0) to endorse the recommendation 2.2.1 to 2.2.6 (as amended)
The Executive Councillor
for Housing approved the recommendations.
Publication date: 05/04/2019
Date of decision: 16/01/2019