To note an update on delivery of previous schemes and to consider a selection of new schemes proposed.
The Committee received a report from the Senior Engineer
(Streets and Open Spaces) regarding the Environmental Improvement Programme
(EIP). The report outlined progress of existing schemes within the east area
and outlined decisions needed around future spending priorities.
Existing Schemes: Progress
The Senior Engineer referred to progress on approved schemes
as set out in his report.
New Schemes That Require Decisions
Members considered a number of 2017/18 schemes put forward
for approval.
In response to questions and comments the Senior Engineer
(Streets and Open Spaces) said the following:
i. The
cost for providing hanging baskets had already been spent in 2017, subject to
area committee approval the cost would be met by the Environmental Improvement
Programme Scheme via a recharge.
ii. Between
10-15% of the cost incurred in providing hanging baskets was in the provision
of the basket and the plants; the remainder of the cost was the servicing,
though the cost would fluctuate dependent on the weather. Efforts had been made
in recent years to conserve water through the type of baskets that had been
purchased.
iii. Stated items
11 and 35 were linked.
iv. Would
investigate why the highway outside of the Post Office on Mill Road had not
been improved.
v. Acknowledged
the Executive Councillor’s for Planning Policy and Transport approval to
undertake a feasibility study to investigate the potential for introducing
screening of the Elizabeth Way Bridge from Abbey Road (E2).
The Committee:
i. Resolved unanimously to:
Note
progress, and delays where experienced, in delivering the identified programme of projects since 2011-12.
ii. Resolved unanimously to:
iii. Support the
allocation of £10,890 in 2017/18 and 2018/19 towards
the provision of 66 summer hanging baskets along Mill Road, subject to 2018/19 budget approval.
iv. Resolved unanimously to:
Continue with
the following schemes as outlined in 5.4 of the Officer report which are as follows:
(11) – Garlic Row / Stanley Road access restrictions (£4,000)
– formal Road Safety Audit needed
from County Council, in order to inform
further consideration of viability for funding through
EIP.
(32) - Mill Road footway grants (£5,300) – continue to offer
opportunity to part-fund selective
improvements to private shop
frontages where supported by traders.
(35) - Oyster Row / Garlic Row access restriction (£23,500)
– formal Road Safety Audit needed from
County Council, in order to inform
further consideration of viability for funding through
EIP.
v. Resolved unanimously to:
Stop the
following scheme as outlined in 5.4 of the Officer’s report which is as follows:
(36) - Riverside parking management (£12,500) – no longer needed in light of developing County Council residents’ parking area proposals.
iv. Resolved unanimously to:
Support the allocation of up to £3,000
funding towards the cost of a feasibility
study to investigate the potential for introducing
screening of the Elizabeth Way Bridge from Abbey
Road (E2).
v. Resolved unanimously to:
Approve the
allocation of remaining EIP funding available in 2017-18 to projects
E3 – E11 for implementation, subject to them
being viable, obtaining consents as necessary, positive consultation and final approval
by Capital Programme Board and
Ward Councillors where required.
vi. Resolved (8 votes to 2) to:
Not to
consider a further application invitation round early in 2018.