Development of land to the rear of 53-55 Wulfstan Way to provide new housing for rent.
This item was Chaired by Councillor Mike Todd-Jones
Matter for
Decision
This report provided details of the indicative capacity study to develop
the vacant land to the rear of 53 and 55 Wulfstan Way
to provide up to 6 new homes. The site was to be brought forward in the
Council’s social housing programme, to be included in the Housing Revenue
Account (HRA) and was recommended to be delivered through Cambridge Investment
Partnership (CIP).
Decision
of Executive Councillor for Housing
i.
Noted the indicative mix of the proposed scheme
ii.
Approved the capital budget of £819,500 for site option 1, detailed in
the report to cover construction costs, professional fees and on costs to
deliver a scheme that meets identified needs of the City.
iii.
Approved that delegated authority be given to the Strategic Director to
enable the site to be developed through Cambridge Investment Partnership.
Reason for the Decision
As set out in the Officer’s report.
Any Alternative Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee received a report from the Trainee Housing Development
Officer.
The Trainee Housing Development Officer said the following in response
to Members’ questions:
i.
The land agreements were being finalised and
discussions were ongoing with residents.
ii.
In response to questions from the committee further
investigation into right of way and access issues would be undertaken.
The Committee unanimously resolved to endorse the recommendations.
The Executive Councillor approved the recommendation.