Council and democracy
Home > Council and Democracy > Decision details
Decision Maker: Executive Councillor for Housing
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Approve the award of a contract(s) to a contractor(s) to carry out structural repairs to the blocks of flats including stabilising or underpinning works to a garage, concrete and brickwork crack repairs and installation of movement joints to each of the blocks, resurfacing external walkways and private terraces, cleaning of external glazing over communal walkways and redecoration of external walls and ceiling surfaces.
Matter for
Decision
The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and associated works is
required to ensure the buildings are maintained in a good state of repair.
Decision
of Executive Councillor for Housing
i.
Approved the award of a contract to Chas Berger Limited,
subject to the completion of the required consultation with leaseholders. Chas
Berger Ltd achieved the highest score following the tender evaluation process.
Reason for the Decision
As set out in the
Officer’s report.
Any Alternative
Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee
received a report from the Asset Manager.
It was noted that
this agenda item had not been included on the Forward Plan for the whole 28-day
requirement before the meeting. This was because pre-tender estimates predicted
a contract value below £1 million. Following tender clarifications, the contract
value would exceed £1 million which changed the category of decision so that it
was now a key decision. With the permission of the Chair of Housing Scrutiny
Committee the urgency procedure was invoked to suspend the 28-day requirement
so that the item could be considered at Committee, so it was open to scrutiny
and debate rather than a decision being made through the out of cycle process.
The Asset Manager and Assistant Director for Housing and Health said the
following in response to Members’ questions:
i.
Noted concerns about some leaseholder’s ability to
be able to pay for the repairs undertaken and advised that the works were not
expected to be completed until April 2026 and therefore bills were not
anticipated to be sent until September 2026. Meetings would take place with
leaseholders to discuss the payment timetable and options for repayment.
Agreements could be made with leaseholders if they were struggling financially.
Repayment would be discussed on an individual basis. Noted that a high proportion
of the Council’s leaseholders rented their properties out.
ii.
Advised that reference to a ‘threshold’ was in
relation to who could make the decision to award the contract. As the contract
value had exceeded £1million this meant that the decision could not be made by
an officer under delegated authority and instead the decision needed to be
brought through Housing Scrutiny Committee and made by the Executive
Councillor.
iii.
Noted that balcony resurfacing had been undertaken
about 10 years previously but there had been some movement in the buildings
since. Repairs wouldn’t be required to all buildings and surveys would be
carried out to see which buildings needed to be repaired.
iv.
The contract was for structural repairs and not
energy efficiency works, however if during the surveys it was found that there
were gaps in cavity wall insulation / loft insulation then the gaps would be
addressed.
v.
Noted concerns regarding the removal and
replacement of trees on the site and advised that a consultation would be
undertaken with residents to ensure suitable trees were provided and a robust
maintenance programme was in place.
The Committee unanimously resolved to endorse the recommendation.
The Executive Councillor
approved the recommendation.
Conflicts of Interest
Declared by the Executive Councillor (and any Dispensations Granted)
No conflicts of interest
were declared by the Executive Councillor.
Publication date: 26/03/2025
Date of decision: 11/03/2025