The Committee is asked to note work undertaken to date and to approve Officer recommendations.
Matter for
Decision
The report seeks approval to proceed with the redevelopment of Davy Road
flats and garages through the Cambridge Investment Partnership to provide 90
new highly sustainable homes on the site. The report also seeks a budget to
purchase the 45 Affordable Homes.
Decision
of Executive Councillor for Housing
ii.
Authorised the Chief Operating Officer in consultation with
the Executive Councillor for Housing to approve variations to the scheme
including the number of units and mix of property types, sizes and tenure as
outlined in the Officer’s report.
iii.
Authorised the Chief Operating Officer in consultation with
the Executive Councillor to approve an Affordable Housing Agreement with CIP
for the purchase of 45 affordable homes. This agreement will be at a value
provided by an independent valuer.
iv.
Approved that delegated authority be given to the Executive
Councillor for Housing in conjunction with the Chief Operating Officer to
enable the site to be developed through Cambridge Investment Partnership (CIP)
subject to a value for money assessment to be carried out on behalf of the
Council.
v.
Approved with immediate effect the purchase of the leasehold
interest of flats at 2-28b Davy Road (evens) and the issue of Home Loss and
Disturbance payments to qualifying Council tenants and Basic Loss and
Disturbance payments to qualifying leaseholders affected by the potential
redevelopment
vi.
Approved giving 32 affected council tenants required to
decant the highest priority on the Council's choice-based lettings system
(Home-Link). The emergency banding status will be applied to all existing
secure tenant applications from 18 September 2024.
vii.
Delegated authority to the Chief Operating Officer to take
steps preparatory to the making of a Compulsory Purchase Order (CPO) in respect
of any Leasehold and Freehold properties required in order to deliver the
scheme.
viii.
Delegated authority to the Chief Operating Officer to make a
CPO in respect of any leasehold or freehold interests that cannot be acquired
by private treaty within a reasonable timescale and at a reasonable cost
subject to the Chief Operating Officer being satisfied that there is a
compelling case in the public interest for the use of compulsory purchase
powers, and that all legal and policy requirements for the making and
confirmation of a CPO have been met;
ix.
Delegated authority to the Chief Operating Officer to serve
initial Demolition Notices under the Housing Act 1985.
Reason for the Decision
As set out in the
Officer’s report.
Any Alternative
Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee
received a report from the Assistant Director
(Development).
The Committee were
reminded that an Equality Impact Assessment had been published separately to
accompany this report.
The Assistant
Director (Development) corrected a typographical error in paragraph 2.1 of the
officer’s report that 9 homes (and not 12 homes) should be eligible for the
Homes England grant funding.
The Assistant Director (Development) said the following in response to
Members’ questions:
i.
Noted members concerns about the reduction in
social rent properties in the council’s portfolio and commented that the number
of social rent properties being built across the country was low as it was
difficult to make this tenure of property financially viable to develop.
ii.
Referred to the table in paragraph 7.1 of the
officer’s report and confirmed that reference made to 100% of residents
experiencing anti-social behaviour should have been clarified to mean 100% of
residents who responded to the consultation.
iii.
Noted concerns raised about works being carried out
to properties which were potentially ear marked for redevelopment and advised
that some works were necessary to ensure homes complied with health and safety
requirements.
iv.
Redevelopment proposals would always consider
retrofit options however it was noted that retrofitting would not always bring
properties up to current levels for example space standards, therefore the case
for redevelopment was strong. The sustainability standard that new homes were
built to was high and it was hoped would future proof homes for a long time.
The Committee resolved by 5 votes to 0
with 3 abstentions to endorse the recommendations.
The Executive Councillor
approved the recommendations.
Conflicts of Interest
Declared by the Executive Councillor (and any Dispensations Granted)
No conflicts of interest
were declared by the Executive Councillor.
Publication date: 07/10/2024
Date of decision: 17/09/2024