Recommended variations to scheme as approved.
This item was chaired by Councillor Pounds (Chair).
Matter for Decision
The report sought approval to proceed with a mixed tenure
scheme at 12-30b Fanshawe Road. This was known as Option B in a report which
was taken to Housing Scrutiny Committee on 21 June 2022.
Decision of Executive Councillor for Housing and
Homelessness
i.
Approved that a mixed tenure scheme be brought
forward in line with the design proposals set out in the Officer’s report.
ii.
Authorised the Assistant Director for Assets and
Property in consultation with the Executive Councillor for housing to approve
variations to the scheme including the number of units, tenure, mix of property
types and sizes outlined in the Officer’s report.
iii.
Authorised the Assistant Director for Assets and
Property in consultation with the Executive Councillor to approve the transfer
of the land known as 12-30b Fanshawe Road and shown edged red on the attached
plan in Appendix 2, to Cambridge Investment Partnership (CIP) for
redevelopment. This transfer will be at a value provided by a further
independent valuation, which will also be approved by CIP Board as detailed in
the financial appraisal set out in Appendix 1. The HRA land receipt will be
incorporated at the minimum value suggested in the appraisal until final valuation
has been received.
iv.
Authorised the Assistant Director for Assets and
Property in consultation with the Executive Councillor to approve the
Affordable Housing Agreement with CIP for the 45 affordable homes. This
agreement would be at a value provided by an independent valuer, to be approved
by CIP Board as detailed in the financial appraisal set out in Appendix 1. This
would mean an amended and reduced budget of £13.0m from £28.5m including decant
costs and other on costs. This budget to be brought forward in the forthcoming
November 2023 Mid Term Financial Strategy.
Reason for the Decision
As set out in the Officer’s report.
Any Alternative Options Considered and Rejected
Not applicable.
Scrutiny Considerations
The Committee received a report from the Assistant Director
Development (Places Group).
The Assistant Director Development (Places Group) said the
following in response to Members’ questions:
i.
9 x 3 bed-flats were proposed within the
Fanshawe Road scheme.
ii. Ward
Councillors would be consulted before a planning application was submitted.
iii. Future
update reports for the housing delivery programme could report information
based on the number of bedrooms a property had.
Councillor Martinelli proposed and Councillor Bennett
seconded an amendment to recommendation ii of the Officer’s report (additional
text underlined,
ii.
Authorise the Assistant Director for Assets and
Property in consultation with the Executive Councillor for Housing and
Homelessness, opposition spokespersons and chair of Housing Scrutiny
Committee to approve variations to the scheme including the number
of units, tenure, mix of property types and sizes outlined in this report.
The amendment was lost by 3 votes in favour to 6 votes
against.
The Committee resolved by 6 votes to 0 with 3 abstentions to
endorse the recommendations.
The Executive Councillor approved the recommendation.
Conflicts of Interest Declared by the Executive
Councillor (and any Dispensations Granted)
No conflicts of interest were declared by the Executive
Councillor.
Publication date: 26/01/2024
Date of decision: 19/09/2023