Regular update on the delivery of new council homes under the 500 programme, together with an update on the work being undertaken to deliver an additional 1,000 Council homes, building on the success of the current programme.
Matter for
Decision
The report provided an update on the housing
development programme.
Decision
of Executive Councillor for Housing
i.
Noted the continued progress on the delivery of the approved
housing programme.
Reason for the Decision
As set out in the
Officer’s report.
Any Alternative
Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee
received a report from the Head of the Housing
Development Agency.
The Head of the Housing Development Agency said the following in
response to Members’ questions:
i.
The housing development programme was a 10-year
programme to deliver 1000 homes. The Council had been fortunate to secure £70
million of funding from the Combined Authority for the previous ‘500 council
homes’ programme. Would report back on further discussions she had with Homes
England regarding further funding bids.
ii.
A planning application for housing development had
been granted at Fen Road. This was one of the schemes Homes England grant
funding had been sought for. If successful, the council hoped to be begin the
development in the summer. An assessment of the need for accessible homes had
been undertaken, larger accessible homes were required. Accessible homes have
generally be provided as 1-2 bed properties.
iii.
The Executive Councillor had met with the
organisation ‘It Takes a City’ to discuss the provision of more modular homes.
It was hoped that more modular homes could be provided once appropriate land
had been identified.
iv.
Properties built through the council’s housing
development programme were built to M42 standard which meant that they could be
adapted in the future. Accessible properties tended to be 10metres larger and
therefore cost more to build. Discussions about suitable locations for modular
homes took place with Ward Councillors. Welcomed a visit with councillors
around the new developments.
v.
New housing development sites were assessed through
the planning process in accordance with the Housing Sustainable Design Guide.
This included an assessment regarding the use of water.
The Committee unanimously resolved to endorse the recommendation.
The Executive Councillor
approved the recommendation.
Conflicts of Interest
Declared by the Executive Councillor (and any Dispensations Granted)
No conflicts of interest
were declared by the Executive Councillor.
Publication date: 04/05/2022
Date of decision: 15/03/2022