Decision Maker: Executive Councillor for Planning, Building Control, and Infrastructure
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
To agree updates to the Local Development Scheme.
Matter for
Decision
To agree an update to the Greater Cambridge Local
Development Scheme (LDS).
Decision of
Executive Councillor for Planning Policy and Open Spaces
i.
Adopted
the updated Local Development Scheme for Greater Cambridge included at Appendix
1 of this report, to take effect from 13 July 2020.
ii.
Delegated
authority to the Joint Director of Planning and Economic Development, in
liaison with the South Cambridgeshire Lead Cabinet member for Planning and the
Cambridge City Council Executive Councillor for Planning Policy and Open Spaces
(and also the Chair and Spokes for the Planning Policy and Transport Scrutiny
Committee), to make any minor editing changes and corrections identified prior
to publication.
Reason for the Decision
As set out in the
Officer’s report.
Any Alternative
Options Considered and Rejected
Not applicable.
Scrutiny
Considerations
The Committee
received a report from the Strategy and Economy
Manager and Planning Policy Manager
The Committee made the following comments in response to the report:
i.
Thought more debate was required on how growth
related to climate change and exploring sustainability means both in social and
environmental aspects. Welcomed what was being proposed as this would give more
time for debate. The change in the
schedule made sense and wanted to harness the contribution of housing from the
AAP into the Local Plan. The timeline seemed to be set by the DCO (Development
Consent Order) process.
ii.
Asked that because of the length of time involved
in the development scheme process that an interim report should be brought back
to Committee in 2021.
The Strategy and Economy Manager and Planning Policy
Manager said the following in response to Members’ questions:
i.
It was good practice at each stage in the local
plan process to reflect and check on the local development scheme.
ii.
When the preferred option report was brought back
to committee a report would be provided to confirm how the programme related to
the local development scheme at that time and whether any further updates were
necessary.
The Committee resolved by 8 votes to 0
to endorse the recommendations.
The Executive Councillor
approved the recommendations.
Conflicts of Interest
Declared by the Executive Councillor (and any Dispensations Granted)
No conflicts of interest
were declared by the Executive Councillor.
Publication date: 20/08/2020
Date of decision: 30/06/2020