received an application for full planning permission.
The application
sought approval for construction of a basement under the front part of
property.
The Planning Officer updated his report by referring to amendments as listed
on the amendment sheet.
The Committee received a representation in objection to the application
from a resident of Canterbury Street.
The representation covered the following issues:
i.
The shared lane was part of the
property of 32 Canterbury Street. It was shared by consent not by right.
ii.
The method of basement
construction was a key factor determining its impact on neighbours. Asked
Councillors not to grant permission without prior detail in the construction
method statement. Took issue with the lack of detail on how enforcement action
would be taken if construction was not undertaken in an appropriate way.
iii.
Took issue with the perceived lack
of detail in the 2006 Local Plan on how basements should be constructed.
Requested the Council developed an up to date policy.
iv.
Suggested the proposal would be
turned down in London and would set a dangerous precedent in Cambridge.
Mr Thompson (Applicant) addressed the Committee in support of the
application.
In response to Member’s comments the Principal Planner proposed
amendments to the Officer’s recommendation:
i.
That condition 5 be amended so wording was in-line with condition 7.
ii.
To include an informative
about public sewerage system.
The amendments were carried
unanimously.
The Committee:
Resolved unanimously (by 7 votes to 0) to grant the
application for planning permission in accordance with the officer
recommendation, for the reasons set out in the officer report, and subject to
the conditions recommended by the officers plus remove condition 6 and add surface
water drainage condition, re-wording of condition 5 and the addition of
informative 9.
Informative numbered No. 9 should be added
to read:
Informative The applicant
should be aware that some parts of the public sewerage system are situated within
the boundary of properties and you must obtain our authorisation to carry out
any building work over or within 3m of the public sewerage system. There are
public sewers running along the highway fronting the property and a sewer
running through the property’s back garden. It is
recommended that the applicant check the location of Anglian Water assets in
relation to their proposed development via digdat – www.digdat.co.uk.
Please note that planning consent does not grant approval to build over
or within 3 metres of a public sewer.